EPA Awards $4.4M Task Order for Peck Iron and Metal Site Remediation Design to HDR APTIM LLC

Contract Overview

Contract Amount: $4,420,276 ($4.4M)

Contractor: HDR Aptim LLC

Awarding Agency: Environmental Protection Agency

Start Date: 2023-04-03

End Date: 2028-04-02

Contract Duration: 1,826 days

Daily Burn Rate: $2.4K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 3

Pricing Type: FIRM FIXED PRICE

Sector: Environmental Services

Official Description: THIS IS A REMEDIAL ACQUISITION FRAMEWORK (RAF) DESIGN AND ENGINEERING SERVICES (DES) TASK ORDER (TO) TO PROVIDE DES SERVICES AT THE PECK IRON AND METAL SITE. THIS TO INCLUDES REQUIREMENTS TO DESIGN THE OU1 REMEDY AND CONDUCT DESIGN SERVICES DURING IM

Place of Performance

Location: ENGLEWOOD, DOUGLAS County, COLORADO, 80112

State: Colorado Government Spending

Plain-Language Summary

Environmental Protection Agency obligated $4.4 million to HDR APTIM LLC for work described as: THIS IS A REMEDIAL ACQUISITION FRAMEWORK (RAF) DESIGN AND ENGINEERING SERVICES (DES) TASK ORDER (TO) TO PROVIDE DES SERVICES AT THE PECK IRON AND METAL SITE. THIS TO INCLUDES REQUIREMENTS TO DESIGN THE OU1 REMEDY AND CONDUCT DESIGN SERVICES DURING IM Key points: 1. The task order focuses on design and engineering services for environmental remediation at the Peck Iron and Metal site. 2. Awarded under a Remedial Acquisition Framework (RAF), indicating a pre-competed contract vehicle. 3. The contract is Firm Fixed Price, providing cost certainty for the government. 4. This acquisition falls within the Environmental Protection Agency's (EPA) broader environmental services sector.

Value Assessment

Rating: good

The $4.42 million task order is for design and engineering services. Benchmarking against similar EPA design contracts would require more granular data on scope and complexity, but the price appears reasonable for a multi-year remediation design project.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The contract was awarded under full and open competition, suggesting a robust price discovery process. The use of a Remedial Acquisition Framework (RAF) implies that the initial competition for the framework itself was extensive, potentially leading to competitive pricing for individual task orders.

Taxpayer Impact: The firm fixed price contract provides cost certainty, protecting taxpayers from potential cost overruns associated with design services for this environmental remediation project.

Public Impact

Addresses environmental cleanup needs at a specific industrial site. Supports the EPA's mission to protect human health and the environment. Ensures necessary design work is completed for effective remediation of contaminated areas. The project's success will be measured by the quality and feasibility of the final design.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Warning Flags

Positive Signals

Sector Analysis

This task order falls within the Environmental Services sector, specifically focusing on remediation and design. Spending in this sector is driven by regulatory requirements and the need to address historical contamination at industrial sites. Benchmarks for similar design contracts vary widely based on site complexity and remediation technology.

Small Business Impact

The data indicates this task order was awarded to HDR APTIM LLC, a large business. There is no specific information provided regarding small business participation or subcontracting goals for this particular task order.

Oversight & Accountability

The EPA is responsible for overseeing this task order. Oversight will likely involve monitoring design progress, ensuring adherence to technical specifications, and managing the firm fixed price budget to ensure effective use of taxpayer funds.

Related Government Programs

Risk Flags

Tags

remediation-services, environmental-protection-agency, co, delivery-order, 1m-plus

Frequently Asked Questions

What is this federal contract paying for?

Environmental Protection Agency awarded $4.4 million to HDR APTIM LLC. THIS IS A REMEDIAL ACQUISITION FRAMEWORK (RAF) DESIGN AND ENGINEERING SERVICES (DES) TASK ORDER (TO) TO PROVIDE DES SERVICES AT THE PECK IRON AND METAL SITE. THIS TO INCLUDES REQUIREMENTS TO DESIGN THE OU1 REMEDY AND CONDUCT DESIGN SERVICES DURING IM

Who is the contractor on this award?

The obligated recipient is HDR APTIM LLC.

Which agency awarded this contract?

Awarding agency: Environmental Protection Agency (Environmental Protection Agency).

What is the total obligated amount?

The obligated amount is $4.4 million.

What is the period of performance?

Start: 2023-04-03. End: 2028-04-02.

What is the estimated cost per acre or per unit of contamination addressed by this design contract?

The provided data does not include specific metrics like cost per acre or per unit of contamination. The total award amount is $4.42 million for design and engineering services at the Peck Iron and Metal site. A detailed cost breakdown or comparison to similar remediation design projects would be needed to establish a meaningful per-unit cost benchmark.

What are the key performance indicators (KPIs) for the design services, and how will their achievement be measured?

Key performance indicators for design services typically include adherence to schedule, budget, technical specifications, and regulatory compliance. While not explicitly detailed in the provided data, the EPA will likely monitor the contractor's progress against the project timeline and ensure the final design meets all environmental and engineering standards required for effective remediation.

How does the cost of this design task order compare to other similar environmental remediation design projects managed by the EPA?

Without specific details on the scope, complexity, and remediation technologies involved at the Peck Iron and Metal site, a direct cost comparison is difficult. However, the $4.42 million award for a 5-year design contract under full and open competition suggests a potentially competitive price point for the services rendered, assuming the scope is comparable to other EPA remediation design projects.

Industry Classification

NAICS: Administrative and Support and Waste Management and Remediation ServicesRemediation and Other Waste Management ServicesRemediation Services

Product/Service Code: NATURAL RESOURCES MANAGEMENTENVIRONMENTAL SYSTEMS PROTECTION

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Solicitation Procedures: SUBJECT TO MULTIPLE AWARD FAIR OPPORTUNITY

Solicitation ID: 68HE0322R0008

Offers Received: 3

Pricing Type: FIRM FIXED PRICE (J)

Evaluated Preference: NONE

Contractor Details

Parent Company: HDR, Inc

Address: 9781 SOUTH MERIDIAN BLVD, STE 400, ENGLEWOOD, CO, 80112

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, U.S.-Owned Business

Financial Breakdown

Contract Ceiling: $5,994,717

Exercised Options: $5,994,717

Current Obligation: $4,420,276

Actual Outlays: $2,343,552

Contract Characteristics

Multi-Year Contract: Yes

Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED

Cost or Pricing Data: YES

Parent Contract

Parent Award PIID: 68HE0318D0009

IDV Type: IDC

Timeline

Start Date: 2023-04-03

Current End Date: 2028-04-02

Potential End Date: 2028-04-02 00:00:00

Last Modified: 2026-01-30

More Contracts from HDR Aptim LLC

View all HDR Aptim LLC federal contracts →

Other Environmental Protection Agency Contracts

View all Environmental Protection Agency contracts →

Explore Related Government Spending