FAA Awards $325K Contract to Burton Construction for Runway Localizer Replacement at Southwest Wyoming Regional Airport
Contract Overview
Contract Amount: $324,947 ($324.9K)
Contractor: Burton Construction, Inc.
Awarding Agency: Department of Transportation
Start Date: 2026-04-06
End Date: 2026-09-30
Contract Duration: 177 days
Daily Burn Rate: $1.8K/day
Competition Type: COMPETED UNDER SAP
Number of Offers Received: 6
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: REPLACEMENT OF THE RUNWAY 27 LOCALIZER (LOC) AT THE SOUTHWEST WYOMING REGIONAL AIRPORT (KRKS) IN ROCK SPRINGS, WYOMING.
Place of Performance
Location: ROCK SPRINGS, SWEETWATER County, WYOMING, 82901
State: Wyoming Government Spending
Plain-Language Summary
Department of Transportation obligated $324,946.9 to BURTON CONSTRUCTION, INC. for work described as: REPLACEMENT OF THE RUNWAY 27 LOCALIZER (LOC) AT THE SOUTHWEST WYOMING REGIONAL AIRPORT (KRKS) IN ROCK SPRINGS, WYOMING. Key points: 1. The contract focuses on critical airport infrastructure, specifically the replacement of a runway localizer system. 2. Burton Construction, Inc. secured this definitive contract valued at $324,946.9. 3. The project is categorized under Power and Communication Line and Related Structures Construction. 4. The contract was competed under SAP (Simplified Acquisition Procedures), indicating a focus on efficient procurement for smaller value contracts.
Value Assessment
Rating: good
The contract value of $324,946.9 appears reasonable for specialized airport infrastructure work. Benchmarking against similar localizer replacement projects would provide further validation, but the use of SAP suggests a streamlined process likely aligned with cost-effectiveness for this contract size.
Cost Per Unit: N/A
Competition Analysis
Competition Level: limited
The contract was competed under SAP, which typically involves a limited number of bidders, often those already registered or known to the agency for specific capabilities. While not full and open competition, SAP aims for efficiency and fair pricing for acquisitions below certain thresholds.
Taxpayer Impact: The investment in airport safety and navigation infrastructure is a necessary public expenditure that ultimately benefits air travelers and the regional economy through improved aviation services.
Public Impact
Enhances aviation safety and navigation reliability at Southwest Wyoming Regional Airport. Supports the modernization of critical airport infrastructure, ensuring compliance with federal standards. Contributes to the operational efficiency of air travel in the Rock Springs, Wyoming area. Potentially reduces flight delays or cancellations due to navigational equipment issues.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for limited competition due to SAP usage.
- Reliance on a single contractor for a critical safety system.
Positive Signals
- Addresses a clear need for infrastructure upgrade.
- Contract awarded to a construction firm.
- Project duration is well-defined.
Sector Analysis
This contract falls within the broader construction and infrastructure sector, specifically related to aviation facilities. Spending benchmarks for airport equipment upgrades vary widely, but projects involving navigational aids like localizers are essential for maintaining air traffic control standards and safety.
Small Business Impact
The data does not indicate whether small businesses were involved in the bidding process or as subcontractors. Further analysis would be needed to determine the extent of small business participation in this specific contract.
Oversight & Accountability
The Federal Aviation Administration (FAA) is responsible for overseeing this contract. Standard procurement regulations and contract management practices would apply to ensure proper execution and accountability for the funds expended.
Related Government Programs
- Power and Communication Line and Related Structures Construction
- Department of Transportation Contracting
- Federal Aviation Administration Programs
Risk Flags
- Potential for schedule delays due to weather or unforeseen site conditions.
- Risk of operational disruptions during construction phases.
- Dependence on a single contractor for critical safety equipment installation.
- Limited competition may impact price discovery.
Tags
power-and-communication-line-and-related, department-of-transportation, wy, definitive-contract, 100k-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Transportation awarded $324,946.9 to BURTON CONSTRUCTION, INC.. REPLACEMENT OF THE RUNWAY 27 LOCALIZER (LOC) AT THE SOUTHWEST WYOMING REGIONAL AIRPORT (KRKS) IN ROCK SPRINGS, WYOMING.
Who is the contractor on this award?
The obligated recipient is BURTON CONSTRUCTION, INC..
Which agency awarded this contract?
Awarding agency: Department of Transportation (Federal Aviation Administration).
What is the total obligated amount?
The obligated amount is $324,946.9.
What is the period of performance?
Start: 2026-04-06. End: 2026-09-30.
What is the specific technical capability of Burton Construction, Inc. that made them the chosen contractor for this specialized localizer replacement project?
The provided data does not detail Burton Construction, Inc.'s specific technical qualifications for replacing a runway localizer. Typically, such contracts require demonstrated experience with aviation navigation systems, adherence to strict FAA standards, and potentially specialized certifications. Further investigation into the contractor's past performance and technical proposals would be necessary to understand their suitability.
How does the $324,946.9 cost compare to the estimated cost or budget allocated for this runway localizer replacement project by the FAA?
The provided data indicates the awarded contract value is $324,946.9. Without knowing the initial cost estimate or the allocated budget for this project, it's difficult to definitively assess if the awarded price represents good value. However, the use of Simplified Acquisition Procedures (SAP) suggests the agency aimed for an efficient and cost-effective procurement within established thresholds.
What are the potential risks associated with the 177-day duration of this project, particularly concerning operational impacts on the airport?
A 177-day project duration for replacing a runway localizer carries risks of potential disruptions to airport operations, including flight delays or temporary runway closures, depending on the construction phasing and mitigation strategies. Weather delays in Wyoming could also extend the timeline. Ensuring robust project management and contingency planning by Burton Construction and the FAA is crucial to minimize these operational impacts.
Industry Classification
NAICS: Construction › Utility System Construction › Power and Communication Line and Related Structures Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: COMPETED UNDER SAP
Solicitation Procedures: SIMPLIFIED ACQUISITION
Solicitation ID: 697DCK-26-R-00162
Offers Received: 6
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 3915 E NEBRASKA AVE, SPOKANE, WA, 99217
Business Categories: American Indian Owned Business, Category Business, Corporate Entity Not Tax Exempt, Minority Owned Business, Native American Owned Business, Small Business, Special Designations, Subchapter S Corporation, U.S.-Owned Business, Woman Owned Business, Women Owned Small Business
Financial Breakdown
Contract Ceiling: $324,947
Exercised Options: $324,947
Current Obligation: $324,947
Contract Characteristics
Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED
Cost or Pricing Data: YES
Timeline
Start Date: 2026-04-06
Current End Date: 2026-09-30
Potential End Date: 2026-09-30 00:00:00
Last Modified: 2026-04-06
More Contracts from Burton Construction, Inc.
- Ehrm IT Closets — $8.3M (Department of Veterans Affairs)
- Project 668-16-105 Renovate LAB and Upgrade Hvac — $2.9M (Department of Veterans Affairs)
- Upgrade Grand Jury Room 227 AT Douglas Usch, Yakima, WA — $50.7K (General Services Administration)
- Excavate Inspect and Fill Voids in the Commercial Lanes. JET and Clean Storm Drain Catch Basins. AT the Sumas Lpoe Station Building 103 Cherry ST Sumas WA 98295 — $48.0K (General Services Administration)
Other Department of Transportation Contracts
- Dafis UDO Reconstruct W/O Advance — $3.8B (Lockheed Martin Services, LLC)
- THE Purpose of This Delivery Order Award IS to ADD Funding for FTI Telecommunications Services — $1.9B (Harris Corporation)
- Provide Funding for Clin 302 for Pre-Flight and In-Flight Services. Contract Number Dtfawa-05-C-00031, Lockheed Martin. POP 01/16/08-03/31/08 — $1.9B (Leidos, Inc.)
- Center for Advanced Aviation Development (caasd) Ffrdc Mitre — $1.7B (THE Mitre Corporation)
- Dafis UDO Reconstruct W/O Advance — $1.5B (Harris Corporation)