DOT Awards $63.8M Contract for Lawton-Fort Sill Airport ATCT Construction

Contract Overview

Contract Amount: $63,866,100 ($63.9M)

Contractor: Structsure Projects Inc

Awarding Agency: Department of Transportation

Start Date: 2025-09-22

End Date: 2028-02-28

Contract Duration: 889 days

Daily Burn Rate: $71.8K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 3

Pricing Type: FIRM FIXED PRICE

Sector: Construction

Official Description: CONSTRUCT A NEW LAW ATCT AT THE LAWTON FORT-SILL REGIONAL AIRPORT IN LAWTON, OK

Place of Performance

Location: LAWTON, COMANCHE County, OKLAHOMA, 73501

State: Oklahoma Government Spending

Plain-Language Summary

Department of Transportation obligated $63.9 million to STRUCTSURE PROJECTS INC for work described as: CONSTRUCT A NEW LAW ATCT AT THE LAWTON FORT-SILL REGIONAL AIRPORT IN LAWTON, OK Key points: 1. The contract value of $63.8 million is significant for a single airport construction project. 2. Structsore Projects Inc. secured the award under full and open competition. 3. The project carries risks associated with large-scale construction timelines and potential cost overruns. 4. The sector is Commercial and Institutional Building Construction, specifically for airport infrastructure.

Value Assessment

Rating: good

The contract value of $63.8 million appears reasonable for a large-scale airport air traffic control tower construction project. Benchmarking against similar projects would provide a more definitive assessment.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The award was made under full and open competition, suggesting a robust price discovery process. This method typically leads to more competitive pricing.

Taxpayer Impact: The firm fixed-price contract aims to protect taxpayers from cost escalations, but the initial award amount represents a substantial commitment of federal funds.

Public Impact

Enhances air traffic control capabilities at Lawton-Fort Sill Regional Airport. Supports regional economic development through construction jobs and improved airport infrastructure. Modernizes critical aviation infrastructure, potentially improving safety and efficiency.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Warning Flags

Positive Signals

Sector Analysis

This project falls within the Commercial and Institutional Building Construction sector, specifically focusing on airport infrastructure. Spending benchmarks for similar large-scale airport construction projects would be relevant for a deeper analysis.

Small Business Impact

The data indicates the prime contractor is Structsore Projects Inc. and that small business participation was not explicitly noted as a requirement or achievement in this award notice. Further investigation into subcontracting opportunities for small businesses would be beneficial.

Oversight & Accountability

The Federal Aviation Administration (FAA) is responsible for overseeing this contract. Standard oversight procedures for large construction projects, including progress monitoring and quality control, should be in place.

Related Government Programs

Risk Flags

Tags

commercial-and-institutional-building-co, department-of-transportation, ok, definitive-contract, 10m-plus

Frequently Asked Questions

What is this federal contract paying for?

Department of Transportation awarded $63.9 million to STRUCTSURE PROJECTS INC. CONSTRUCT A NEW LAW ATCT AT THE LAWTON FORT-SILL REGIONAL AIRPORT IN LAWTON, OK

Who is the contractor on this award?

The obligated recipient is STRUCTSURE PROJECTS INC.

Which agency awarded this contract?

Awarding agency: Department of Transportation (Federal Aviation Administration).

What is the total obligated amount?

The obligated amount is $63.9 million.

What is the period of performance?

Start: 2025-09-22. End: 2028-02-28.

What is the historical cost performance of Structsore Projects Inc. on similar federal construction contracts?

Analyzing Structsore Projects Inc.'s past performance on comparable federal construction projects is crucial. This includes examining their track record for on-time delivery, adherence to budget, and quality of work. A history of successful project completion suggests a lower risk profile for this new contract, while past issues could indicate potential challenges ahead.

How does the awarded price compare to independent cost estimates for constructing an ATCT of this size and complexity?

Comparing the $63.8 million award to independent cost estimates is vital for assessing value. If the award is significantly higher than estimates, it could signal potential overpricing or unforeseen complexities. Conversely, a price below estimates might indicate aggressive bidding or potential risks to quality or schedule if the contractor underestimated costs.

What are the specific performance metrics and milestones tied to the firm fixed-price contract to ensure timely and effective project completion?

Understanding the specific performance metrics and milestones within the firm fixed-price contract is key to evaluating effectiveness. These should include clear deliverables, quality standards, and schedule checkpoints. Robust oversight by the FAA to track progress against these milestones is essential for ensuring the project is completed on time, within budget, and to the required specifications.

Industry Classification

NAICS: ConstructionNonresidential Building ConstructionCommercial and Institutional Building Construction

Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIESCONSTRUCTION OF BUILDINGS

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE

Solicitation ID: 697DCK-25-R-00367

Offers Received: 3

Pricing Type: FIRM FIXED PRICE (J)

Evaluated Preference: NONE

Contractor Details

Address: 903 E 104TH ST, KANSAS CITY, MO, 64131

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, Subchapter S Corporation, U.S.-Owned Business

Financial Breakdown

Contract Ceiling: $63,866,100

Exercised Options: $63,866,100

Current Obligation: $63,866,100

Actual Outlays: $393,978

Contract Characteristics

Commercial Item: COMMERCIAL PRODUCTS/SERVICES

Cost or Pricing Data: NO

Timeline

Start Date: 2025-09-22

Current End Date: 2028-02-28

Potential End Date: 2028-02-28 00:00:00

Last Modified: 2026-01-26

More Contracts from Structsure Projects Inc

View all Structsure Projects Inc federal contracts →

Other Department of Transportation Contracts

View all Department of Transportation contracts →

Explore Related Government Spending