EPA's $44.5M Remediation Services Contract with Weston Solutions Inc. Faced Concerns Over Time and Materials Pricing
Contract Overview
Contract Amount: $44,469,285 ($44.5M)
Contractor: Weston Solutions Inc
Awarding Agency: Environmental Protection Agency
Start Date: 2006-09-28
End Date: 2014-10-10
Contract Duration: 2,934 days
Daily Burn Rate: $15.2K/day
Number of Offers Received: 2
Pricing Type: TIME AND MATERIALS
Sector: Other
Official Description: PERFORMANCE BASED SERVICES
Place of Performance
Location: VERNON HILLS, LAKE County, ILLINOIS, 60061
State: Illinois Government Spending
Plain-Language Summary
Environmental Protection Agency obligated $44.5 million to WESTON SOLUTIONS INC for work described as: PERFORMANCE BASED SERVICES Key points: 1. Contract value of $44.5 million over 8 years. 2. Sole-source award to Weston Solutions Inc. for remediation services. 3. Significant duration (2934 days) raises questions about efficiency. 4. Time and Materials pricing structure can lead to cost overruns.
Value Assessment
Rating: questionable
The contract utilized a Time and Materials (T&M) pricing structure, which is often less cost-effective than fixed-price contracts for well-defined services. Without clear benchmarks or competitive bidding, assessing the value for money is difficult, especially given the long duration.
Cost Per Unit: N/A
Competition Analysis
Competition Level: sole-source
This was a sole-source award, limiting competitive pressure on pricing. The T&M structure further complicates price discovery, as costs are tied to labor hours and material usage rather than a pre-agreed scope and price.
Taxpayer Impact: The lack of competition and the T&M pricing model likely resulted in higher costs for taxpayers compared to a competitively bid, fixed-price contract.
Public Impact
Environmental cleanup services impacting public health and safety. Long-term contract duration suggests complex or ongoing environmental issues. Potential for cost overruns due to T&M pricing affects taxpayer burden.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Sole-source award
- Time and Materials pricing
- Long contract duration
- Lack of competition
Positive Signals
- Performance-based services (though T&M can undermine this)
- Awarded by EPA, a key environmental agency
Sector Analysis
Environmental remediation services are critical for addressing pollution and protecting public health. Spending in this sector can vary widely based on the scale and complexity of environmental challenges. This contract's value is moderate for a long-term remediation project.
Small Business Impact
The data does not indicate any specific provisions or awards made to small businesses under this contract, suggesting it was likely not a focus area.
Oversight & Accountability
The sole-source nature and T&M pricing warrant scrutiny. Oversight would be crucial to ensure efficient use of funds and prevent potential cost creep. The contract's long duration necessitates ongoing monitoring.
Related Government Programs
- Remediation Services
- Environmental Protection Agency Contracting
- Environmental Protection Agency Programs
Risk Flags
- Sole-source award lacks competition.
- Time and Materials pricing is prone to cost overruns.
- Long contract duration (8 years) increases risk.
- Lack of clear performance metrics in provided data.
- Potential for inefficient service delivery.
Tags
remediation-services, environmental-protection-agency, il, delivery-order, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Environmental Protection Agency awarded $44.5 million to WESTON SOLUTIONS INC. PERFORMANCE BASED SERVICES
Who is the contractor on this award?
The obligated recipient is WESTON SOLUTIONS INC.
Which agency awarded this contract?
Awarding agency: Environmental Protection Agency (Environmental Protection Agency).
What is the total obligated amount?
The obligated amount is $44.5 million.
What is the period of performance?
Start: 2006-09-28. End: 2014-10-10.
What was the justification for the sole-source award, and were alternative competitive approaches considered?
Sole-source awards are typically granted when only one responsible source is available or when a compelling justification exists, such as unique capabilities or urgent needs. Without further documentation, it's unclear if alternatives were explored. This lack of competition raises concerns about potential overpayment and reduced innovation.
How effectively did the Time and Materials pricing control costs for remediation services over the contract's long duration?
Time and Materials contracts can be problematic for long-term projects as they incentivize longer durations and higher material usage rather than efficient completion. Effective oversight, including detailed cost tracking and justification for hours/materials, would be essential to mitigate risks of inflated costs and ensure value for taxpayer money.
What environmental outcomes were achieved, and did the contract deliver value commensurate with its $44.5 million cost?
Assessing the value requires comparing the achieved environmental remediation outcomes against the total expenditure. Without specific performance metrics and independent verification of results, it's difficult to definitively state if the $44.5 million delivered commensurate value. The T&M structure complicates this assessment.
Industry Classification
NAICS: Administrative and Support and Waste Management and Remediation Services › Remediation and Other Waste Management Services › Remediation Services
Product/Service Code: TECHNICAL REPRESENTATIVE SVCS. › TECHNICAL REPRESENTATIVE SERVICES
Contractor Details
Parent Company: Weston Solutions Holdings, Inc. (UEI: 118341234)
Address: 1400 WESTON WAY, WEST CHESTER, PA, 19380
Business Categories: Category Business, Not Designated a Small Business
Financial Breakdown
Contract Ceiling: $47,099,285
Exercised Options: $47,099,285
Current Obligation: $44,469,285
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Parent Contract
Parent Award PIID: EPS50604
IDV Type: IDC
Timeline
Start Date: 2006-09-28
Current End Date: 2014-10-10
Potential End Date: 2014-10-10 00:00:00
Last Modified: 2020-03-06
More Contracts from Weston Solutions Inc
- !!pr-Powerfy23!! Temporary Power Generation AT the Palo Seco Power Plant — $797.1M (Department of Defense)
- !!pr-Powerfy23!! Temporary Power Generation AT the SAN Juan Power Plant — $593.9M (Department of Defense)
- Temporary Power for 2 Months for Puerto Rico in Support of Hurricane Maria Recovery Efforts — $218.4M (Department of Defense)
- Federal Contract — $181.4M (Environmental Protection Agency)
- TAS::96 3135::TAS, TAS::96 3134::TAS, Task Order for Design-Build Matoc - Recovery - Hgnc, Multiple Site Repairs in Harris and Chambers Counties, Texas — $100.0M (Department of Defense)
Other Environmental Protection Agency Contracts
- Remedial Action Contract 2 — $383.3M (CH2M Hill, Inc)
- A&E Services — $309.2M (Sultrac, JV)
- Federal Contract — $181.4M (Weston Solutions Inc)
- Central Data Exchange (CDX) Support Services — $160.9M (CGI Federal Inc.)
- This Remedial Action Contract 2 Full Service (RAC 2 FS) for Epa's Region 8 Provides Professional Architect/Engineer, Technical, and Management Services to Support Remedial Response, Enforcement Oversight and Non-Time Critical Removal Activities Under Cercla, AS Amended by Sara; and the Robert T. Stafford Disaster Relief and Emergency Assistance ACT Pursuant to the Federal Response Plan (FRP) and Other Laws to Help Address And/Or Mitigate Endangerment to the Public Health, Welfare or Environment, and to Support States and Communities in Preparing for Responses to Releases of Hazardous Substances, AS Well AS Counter-Terrorism — $145.9M (CDM Federal Programs Corporation)