DoD Awards $14.8M for Boliver Placement Area Repairs to Weston Solutions Inc
Contract Overview
Contract Amount: $14,811,675 ($14.8M)
Contractor: Weston Solutions Inc
Awarding Agency: Department of Defense
Start Date: 2009-11-25
End Date: 2010-10-30
Contract Duration: 339 days
Daily Burn Rate: $43.7K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 8
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: TAS ::96 3135::TAS ROLLOVER PASS TO BOLIVER PLACEMENT AREA REPAIRS.
Place of Performance
Location: GALVESTON, GALVESTON County, TEXAS, 77553
State: Texas Government Spending
Plain-Language Summary
Department of Defense obligated $14.8 million to WESTON SOLUTIONS INC for work described as: TAS ::96 3135::TAS ROLLOVER PASS TO BOLIVER PLACEMENT AREA REPAIRS. Key points: 1. Spending focuses on infrastructure repair within the Department of the Army. 2. Weston Solutions Inc. secured the contract through full and open competition. 3. The contract value is substantial for a single delivery order. 4. The project falls under the Highway, Street, and Bridge Construction sector.
Value Assessment
Rating: good
The contract value of $14.8 million for a 339-day duration appears reasonable for a construction project of this nature. Benchmarking against similar bridge and infrastructure repair contracts would provide a more precise assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded using full and open competition, suggesting a robust price discovery process. This method typically leads to competitive pricing as multiple bidders vie for the contract.
Taxpayer Impact: Taxpayer funds were utilized through a competitive bidding process, aiming for cost-effectiveness in infrastructure repair.
Public Impact
Infrastructure improvements at Boliver Placement Area enhance operational readiness. Local and regional construction firms may have participated in the bidding process. The project supports the Department of Defense's infrastructure maintenance mission.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for cost overruns in construction projects.
- Contract duration may be subject to weather or unforeseen site conditions.
Positive Signals
- Awarded through full and open competition.
- Firm fixed price contract provides cost certainty.
Sector Analysis
This contract falls within the Construction sector, specifically focusing on highway, street, and bridge construction. Spending in this sector is critical for maintaining essential infrastructure, with benchmarks varying widely based on project scope and location.
Small Business Impact
While the contract was awarded through full and open competition, there is no specific indication of small business participation or subcontracting goals in the provided data. Further analysis would be needed to determine the extent of small business involvement.
Oversight & Accountability
The contract was awarded by the Department of the Army, implying oversight from relevant military and civilian contracting authorities. The firm fixed price structure offers some accountability on cost.
Related Government Programs
- Highway, Street, and Bridge Construction
- Department of Defense Contracting
- Department of the Army Programs
Risk Flags
- Construction project risks (delays, cost overruns).
- Potential for unforeseen site conditions.
- Contract duration is relatively short for major repairs.
- Lack of detail on specific repair scope.
Tags
highway-street-and-bridge-construction, department-of-defense, tx, delivery-order, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $14.8 million to WESTON SOLUTIONS INC. TAS ::96 3135::TAS ROLLOVER PASS TO BOLIVER PLACEMENT AREA REPAIRS.
Who is the contractor on this award?
The obligated recipient is WESTON SOLUTIONS INC.
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Army).
What is the total obligated amount?
The obligated amount is $14.8 million.
What is the period of performance?
Start: 2009-11-25. End: 2010-10-30.
What was the specific scope of work for the Boliver Placement Area repairs?
The provided data indicates the contract is for 'TAS ROLLOVER PASS TO BOLIVER PLACEMENT AREA REPAIRS.' While the exact nature of 'TAS ROLLOVER PASS' is unclear without further context, it strongly suggests repairs related to an access point, passage, or potentially a specific type of infrastructure within the Boliver Placement Area, likely involving construction or structural work.
Were there any performance issues or disputes during the contract period?
The provided data does not contain information regarding performance issues, disputes, or contract modifications. A thorough review of contract performance reports, payment histories, and any associated documentation would be necessary to assess any potential problems or successes during the contract's execution.
How does the awarded amount compare to the initial estimated cost for this project?
The data does not include the initial estimated cost for the project. To assess the value proposition, a comparison between the awarded amount of $14.8 million and the government's original cost estimate would be required. This comparison would reveal if the contract was awarded significantly above, below, or at the estimated budget.
Industry Classification
NAICS: Construction › Highway, Street, and Bridge Construction › Highway, Street, and Bridge Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCT NONBUILDING FACILITIES
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE
Offers Received: 8
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Parent Company: Weston Solutions Holdings, Inc. (UEI: 118341234)
Address: 5599 SAN FELIPE ST STE 700, HOUSTON, TX, 77056
Business Categories: Category Business, Not Designated a Small Business
Financial Breakdown
Contract Ceiling: $14,811,675
Exercised Options: $14,811,675
Current Obligation: $14,811,675
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Cost or Pricing Data: NO
Parent Contract
Parent Award PIID: W912BV08D2022
IDV Type: IDC
Timeline
Start Date: 2009-11-25
Current End Date: 2010-10-30
Potential End Date: 2010-10-30 00:00:00
Last Modified: 2021-03-28
More Contracts from Weston Solutions Inc
- !!pr-Powerfy23!! Temporary Power Generation AT the Palo Seco Power Plant — $797.1M (Department of Defense)
- !!pr-Powerfy23!! Temporary Power Generation AT the SAN Juan Power Plant — $593.9M (Department of Defense)
- Temporary Power for 2 Months for Puerto Rico in Support of Hurricane Maria Recovery Efforts — $218.4M (Department of Defense)
- Federal Contract — $181.4M (Environmental Protection Agency)
- TAS::96 3135::TAS, TAS::96 3134::TAS, Task Order for Design-Build Matoc - Recovery - Hgnc, Multiple Site Repairs in Harris and Chambers Counties, Texas — $100.0M (Department of Defense)
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)