DOT Awards $23M for Natchez Trace Parkway Drainage Improvements, Covering 83 Miles
Contract Overview
Contract Amount: $23,064,071 ($23.1M)
Contractor: Estes Bros. Const. Inc.
Awarding Agency: Department of Transportation
Start Date: 2024-06-03
End Date: 2028-01-31
Contract Duration: 1,337 days
Daily Burn Rate: $17.3K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 3
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: PROJECT NP NATR 3N17, 3H26, ETC. - THE PROJECT CONSISTS OF THE DRAINAGE IMPROVEMENTS OF THE NATCHEZ TRACE PARKWAY (NATR) FROM MILEPOST (MP) 121 TO MP 204 INCLUDING SOME PARKING AREAS. THE WORK CONSISTS OF DESIGN AND INSTALLATION OF DESIGNATED INLETS
Place of Performance
Location: KOSCIUSKO, ATTALA County, MISSISSIPPI, 39090
Plain-Language Summary
Department of Transportation obligated $23.1 million to ESTES BROS. CONST. INC. for work described as: PROJECT NP NATR 3N17, 3H26, ETC. - THE PROJECT CONSISTS OF THE DRAINAGE IMPROVEMENTS OF THE NATCHEZ TRACE PARKWAY (NATR) FROM MILEPOST (MP) 121 TO MP 204 INCLUDING SOME PARKING AREAS. THE WORK CONSISTS OF DESIGN AND INSTALLATION OF DESIGNATED INLETS Key points: 1. Significant infrastructure investment in Mississippi's Natchez Trace Parkway. 2. Competition was full and open, suggesting potential for competitive pricing. 3. Risk appears moderate, focusing on construction execution and weather delays. 4. Sector is Highway, Street, and Bridge Construction, a critical infrastructure area.
Value Assessment
Rating: good
The contract's firm fixed price structure provides cost certainty. Benchmarking against similar large-scale highway construction projects is needed for a definitive value assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
Full and open competition was utilized, allowing multiple bidders to participate. This method generally promotes competitive pricing and ensures the government receives fair market value.
Taxpayer Impact: Taxpayer funds are being used for essential infrastructure maintenance and improvement, enhancing the longevity and safety of a national parkway.
Public Impact
Enhances safety and accessibility of the Natchez Trace Parkway. Supports local economy through construction jobs and material sourcing. Preserves a significant historical and recreational resource for public use. Addresses critical drainage issues to prevent erosion and road damage.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for construction delays due to weather or unforeseen site conditions.
- Contract duration is substantial, requiring ongoing monitoring.
- Scope definition for 'some parking areas' could lead to change orders.
Positive Signals
- Firm fixed price contract limits cost overrun risk for the government.
- Full and open competition suggests a competitive award price.
- Project addresses essential infrastructure maintenance needs.
Sector Analysis
This project falls within the Highway, Street, and Bridge Construction sector, which is vital for national transportation networks. Spending in this sector often fluctuates with infrastructure initiatives and economic conditions.
Small Business Impact
While the prime contractor is Estes Bros. Const. Inc., the data does not specify subcontracting goals or participation by small businesses in this particular contract. Further review would be needed to assess small business impact.
Oversight & Accountability
The Federal Highway Administration is the contracting agency, responsible for oversight. The definitive contract award suggests a structured process, but ongoing monitoring of performance and adherence to schedule is crucial.
Related Government Programs
- Highway, Street, and Bridge Construction
- Department of Transportation Contracting
- Federal Highway Administration Programs
Risk Flags
- Contract duration of over 3 years.
- Potential for weather-related delays in Mississippi.
- Scope ambiguity in 'some parking areas'.
- Large geographical area of work (83 miles).
Tags
highway-street-and-bridge-construction, department-of-transportation, ms, definitive-contract, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Transportation awarded $23.1 million to ESTES BROS. CONST. INC.. PROJECT NP NATR 3N17, 3H26, ETC. - THE PROJECT CONSISTS OF THE DRAINAGE IMPROVEMENTS OF THE NATCHEZ TRACE PARKWAY (NATR) FROM MILEPOST (MP) 121 TO MP 204 INCLUDING SOME PARKING AREAS. THE WORK CONSISTS OF DESIGN AND INSTALLATION OF DESIGNATED INLETS
Who is the contractor on this award?
The obligated recipient is ESTES BROS. CONST. INC..
Which agency awarded this contract?
Awarding agency: Department of Transportation (Federal Highway Administration).
What is the total obligated amount?
The obligated amount is $23.1 million.
What is the period of performance?
Start: 2024-06-03. End: 2028-01-31.
What is the historical cost performance of Estes Bros. Const. Inc. on similar federal contracts?
Analyzing the contractor's past performance on comparable federal projects is essential to gauge their reliability and cost control capabilities. This includes reviewing past contract values, completion times, and any documented issues or disputes. A strong track record suggests a lower risk of cost overruns and schedule delays for this current drainage improvement project.
How will potential environmental impacts during construction be mitigated?
Drainage improvements can have environmental implications, particularly concerning water runoff and potential disruption to local ecosystems. The contract should detail specific mitigation measures, such as sediment control, erosion prevention, and waste management plans. The agency's oversight will be critical in ensuring compliance with environmental regulations and minimizing any negative ecological effects.
What is the projected long-term benefit of these drainage improvements to the Parkway's infrastructure?
The primary benefit is the prevention of further erosion and structural damage to the Natchez Trace Parkway caused by inadequate drainage. This investment is expected to extend the lifespan of the roadway and associated parking areas, reducing future maintenance costs and ensuring continued safe access for visitors. Quantifying the avoided costs from potential future repairs would highlight the project's long-term value.
Industry Classification
NAICS: Construction › Highway, Street, and Bridge Construction › Highway, Street, and Bridge Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: TWO STEP
Solicitation ID: 693C7324R000004
Offers Received: 3
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 126 SUGAR RUN RD, JONESVILLE, VA, 24263
Business Categories: Category Business, Corporate Entity Not Tax Exempt, HUBZone Firm, Self-Certified Small Disadvantaged Business, Small Business, Special Designations, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $23,064,071
Exercised Options: $23,064,071
Current Obligation: $23,064,071
Actual Outlays: $16,598,117
Contract Characteristics
Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED
Cost or Pricing Data: NO
Timeline
Start Date: 2024-06-03
Current End Date: 2028-01-31
Potential End Date: 2028-01-31 00:00:00
Last Modified: 2026-01-21
More Contracts from Estes Bros. Const. Inc.
- Project: NP NP Blri 1L9, 1M22, ETC - the Project Consists of the Rehabilitation of Approximately 24 Miles of the Blue Ridge Parkway (blri) Between Milepost (MP) 97 and 121 in Bedford, Botetourt, and Roanoke Counties, Virginia. the Work Consists of RE — $64.3M (Department of Transportation)
- TO Solicit Project: Np-Natr 2A18,B7,C6,D11,3A17,B9 — $62.1M (Department of Transportation)
- NP Natr 3N18, 3H27, ETC - Geotechnical, Pavement Rehabilitation, and Structural Repairs Between MP 121 and MP 204 (phase 2), Project MS NP Natr 3N18 3H27 ETC, Solicitation Number 693C73-25-B-000003, Located in Attala, Choctaw, Leake, Madison, and WEB — $32.6M (Department of Transportation)
- Project Np-Foot 8G16, 8H10: the Work Includes Full Depth Reclamation of Foothills Parkway Sections 8G and 8H Mainline, Parking Areas, and Pull-Offs; Establishing Roadside Ditches and Reconditioning Paved Waterways; Replacing Signs and Pavement Marki — $28.6M (Department of Transportation)
- Project TN Erfo FS 2019-1(2): the Project Consists of Reconstructing Sink Mountain Launch Road and Constructing a NEW Parking Area. the Work Includes Clearing and Grubbing, Embankment Construction, Asphalt Pavement, Reinforced Concrete BOX Culvert I — $3.2M (Department of Transportation)
Other Department of Transportation Contracts
- Dafis UDO Reconstruct W/O Advance — $3.8B (Lockheed Martin Services, LLC)
- THE Purpose of This Delivery Order Award IS to ADD Funding for FTI Telecommunications Services — $1.9B (Harris Corporation)
- Provide Funding for Clin 302 for Pre-Flight and In-Flight Services. Contract Number Dtfawa-05-C-00031, Lockheed Martin. POP 01/16/08-03/31/08 — $1.9B (Leidos, Inc.)
- Center for Advanced Aviation Development (caasd) Ffrdc Mitre — $1.7B (THE Mitre Corporation)
- Dafis UDO Reconstruct W/O Advance — $1.5B (Harris Corporation)