Agriculture Awards $82.3M for GWCC Building Renovations Under Full and Open Competition
Contract Overview
Contract Amount: $82,306,076 ($82.3M)
Contractor: Grunley Construction CO., Inc.
Awarding Agency: Department of Agriculture
Start Date: 2020-08-20
End Date: 2024-01-31
Contract Duration: 1,259 days
Daily Burn Rate: $65.4K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 3
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: THE INTENT OF THIS PROJECT IS TO RENOVATE ALL FOUR GWCC BUILDINGS IN A TWO-PHASE CONSTRUCTION APPROACH:
Place of Performance
Location: COLLEGE PARK, PRINCE GEORGES County, MARYLAND, 20740
State: Maryland Government Spending
Plain-Language Summary
Department of Agriculture obligated $82.3 million to GRUNLEY CONSTRUCTION CO., INC. for work described as: THE INTENT OF THIS PROJECT IS TO RENOVATE ALL FOUR GWCC BUILDINGS IN A TWO-PHASE CONSTRUCTION APPROACH: Key points: 1. Significant investment in facility modernization for the Government-wide Conference Center Complex (GWCC). 2. Grunley Construction Co., Inc. secured the contract through a competitive bidding process. 3. The project spans multiple years, indicating a substantial and complex undertaking. 4. Firm Fixed Price contract type suggests cost certainty for the government.
Value Assessment
Rating: good
The award amount of $82.3 million for a multi-phase renovation project appears reasonable given the scope and duration. Benchmarking against similar large-scale government building renovations would provide a more precise assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under full and open competition, indicating a robust price discovery process. This method generally leads to more competitive pricing by allowing all eligible contractors to bid.
Taxpayer Impact: The competitive nature of the award is expected to yield a fair price, maximizing taxpayer value for the renovation services.
Public Impact
Modernized facilities will improve government conference capabilities. Potential for job creation within the construction sector in Maryland. Ensures long-term usability and reduced maintenance costs for critical government infrastructure.
Waste & Efficiency Indicators
Waste Risk Score: 75 / 10
Positive Signals
- Full and open competition
- Firm Fixed Price contract
- Significant investment in infrastructure
Sector Analysis
This contract falls under Industrial Building Construction, a sector often characterized by large-scale projects and significant capital investment. The $82.3 million award is substantial for a single project within this category.
Small Business Impact
The provided data does not indicate whether small businesses were involved as subcontractors. Further analysis would be needed to determine the extent of small business participation in this large construction project.
Oversight & Accountability
The contract was awarded by the Department of Agriculture's Office of the Chief Financial Officer, suggesting established oversight mechanisms. The duration and phased approach will require ongoing monitoring.
Related Government Programs
- Industrial Building Construction
- Department of Agriculture Contracting
- Office of the Chief Financial Officer Programs
Risk Flags
- Long project duration (1259 days) increases risk of cost overruns or scope creep.
- Potential for unforeseen issues during renovation of existing buildings.
- Dependence on a single prime contractor for a large, multi-phase project.
Tags
industrial-building-construction, department-of-agriculture, md, definitive-contract, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Agriculture awarded $82.3 million to GRUNLEY CONSTRUCTION CO., INC.. THE INTENT OF THIS PROJECT IS TO RENOVATE ALL FOUR GWCC BUILDINGS IN A TWO-PHASE CONSTRUCTION APPROACH:
Who is the contractor on this award?
The obligated recipient is GRUNLEY CONSTRUCTION CO., INC..
Which agency awarded this contract?
Awarding agency: Department of Agriculture (Office of the Chief Financial Officer).
What is the total obligated amount?
The obligated amount is $82.3 million.
What is the period of performance?
Start: 2020-08-20. End: 2024-01-31.
What is the projected return on investment for these renovations in terms of operational efficiency and cost savings?
The return on investment is not explicitly detailed in the provided data. However, renovations typically aim to improve energy efficiency, reduce long-term maintenance costs, and enhance the functionality of the buildings, indirectly contributing to operational efficiency and cost savings over the lifespan of the modernized facilities.
What are the key performance indicators (KPIs) being used to measure the success of this renovation project?
Specific KPIs are not detailed. Generally, success would be measured by adherence to schedule, budget compliance, quality of construction meeting specified standards, minimal disruption to ongoing operations, and post-renovation performance metrics related to energy usage and facility functionality.
How will the phased approach impact the overall cost and timeline of the project?
A phased approach can help manage complexity and minimize disruption, potentially controlling costs by allowing for focused resource allocation. However, it can also extend the overall project timeline and may introduce coordination challenges between phases, potentially impacting the total cost if not managed effectively.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Industrial Building Construction
Product/Service Code: MAINT, REPAIR, ALTER REAL PROPERTY › MAINT, ALTER, REPAIR NONBUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE
Solicitation ID: 12314420B0001
Offers Received: 3
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 15020 SHADY GROVE RD STE 500, ROCKVILLE, MD, 20850
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, Subchapter S Corporation, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $82,306,076
Exercised Options: $82,306,076
Current Obligation: $82,306,076
Actual Outlays: $82,306,076
Subaward Activity
Number of Subawards: 30
Total Subaward Amount: $63,219,290
Contract Characteristics
Multi-Year Contract: Yes
Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED
Cost or Pricing Data: NO
Timeline
Start Date: 2020-08-20
Current End Date: 2024-01-31
Potential End Date: 2025-02-01 00:00:00
Last Modified: 2025-02-10
More Contracts from Grunley Construction CO., Inc.
- Eeob Modernization, Phase III — $212.9M (General Services Administration)
- Design-Build of Historic Center Building, ST Elizabeths West Campus, SE, Wash., DC / Project Funded — $206.4M (General Services Administration)
- Contracting Officer Authority WAS Transferred to Bonnie Echoloes — $205.7M (General Services Administration)
- Phase II, State Place Modernization — $166.8M (General Services Administration)
- Design/Build-Briding Services for the Consumer Financial Protection Bureau Headquarters Renovation Project — $144.9M (General Services Administration)
Other Department of Agriculture Contracts
- Usda Enterprise-Scale Fedramp Certified Cloud Hosting Services. Igf::ot::igf — $336.8M (Accenture Federal Services LLC)
- Usda Disc Enterprise Wide Salesforce Software&support Services — $294.8M (Carahsoft Technology Corp)
- Provide Removal of Carcasses AT Premise X Igf::ot::igf Hpai — $292.5M (Clean Harbors Environmental Services Inc)
- Financial Management Modernization Initiative — $291.0M (Accenture LLP)
- Enterprise Application Services — $273.5M (Synergy Business Innovation & Solutions Inc.)