Total Contract Value: $40,367,569,662
Contract Count: 26
Average Contract Size: $1.6B
Sole Source Rate: 0%
Small Business Rate: 0%
Spending by Sector
- Defense: $26.8B (8 contracts)
- Other: $12.3B (10 contracts)
- R&D: $1.3B (7 contracts)
- Engineering Services: $12.7M (1 contracts)
Contracts
- INTERNATIONAL SPACE STATION — $22.4B
- PROVIDE DEVELOPMENTAL HARDWARE AND TEST ARTICLES, AND MANUFACTURE AND ASSEMBLE ARES I UPPER STAGES. THE UPPER STAGE (US) ELEMENT IS AN INTEGRAL PART OF THE ARES I LAUNCH VEHICLE AND PROVIDES THE SECOND STAGE OF FLIGHT. THE US ELEMENT IS RESPONSIBLE FOR THE ROLL CONTROL DURING THE FIRST STAGE BURN AND SEPARATION; AND WILL PROVIDE THE GUIDANCE AND NAVIGATION, COMMAND AND DATA HANDLING, AND OTHER AVIONICS FUNCTIONS FOR THE ARES I DURING ALL PHASES OF THE ASCENT FLIGHT. THE US ELEMENT IS A NEW DESIGN THAT EMPHASIZES SAFETY, OPERABILITY, AND MINIMUM LIFE CYCLE COST. THE OVERALL DESIGN, DEVELOPMENT, TEST AND EVALUATION (DDT&E), PRODUCTION, AND SUSTAINING ENGINEERING EFFORTS INCLUDE ACTIVITIES PERFORMED BY THREE ORGANIZATIONS; THE NASA DESIGN TEAM (NDT), THE UPPER STAGE PRODUCTION CONTRACTOR (USPC) AND THE INSTRUMENT UNIT PRODUCTION CONTRACTOR (IUPC). FOR CLARITY, THE USPC WILL BE REFERRED TO AS THE CONTRACTOR THROUGHOUT THIS DOCUMENT. NASA IS RESPONSIBLE FOR THE INTEGRATION OF THE PRIMARY ELEMENTS OF THE ARES I LAUNCH VEHICLE INCLUDING: THE FIRST STAGE, US INCLUDING INSTRUMENT UNIT (IU), AND US ENGINE; AND WILL ALSO INTEGRATE THE ARES I LAUNCH VEHICLE AT THE LAUNCH SITE. NASA IS RESPONSIBLE FOR THE DDT&E, INCLUDING TECHNICAL AND PROGRAMMATIC INTEGRATION OF THE US SUBSYSTEMS AND GOVERNMENT-FURNISHED PROPERTY. NASA WILL LEAD THE EFFORT TO DEVELOP THE REQUIREMENTS AND SPECIFICATIONS OF THE US ELEMENT, THE DEVELOPMENT PLAN AND TESTING REQUIREMENTS, AND ALL DESIGN DOCUMENTATION, INITIAL MANUFACTURING AND ASSEMBLY PROCESS PLANNING, LOGISTICS PLANNING, AND OPERATIONS SUPPORT PLANNING. DEVELOPMENT, QUALIFICATION, AND ACCEPTANCE TESTING WILL BE CONDUCTED BY NASA AND THE CONTRACTOR TO SATISFY REQUIREMENTS AND FOR RISK MITIGATION. NASA IS RESPONSIBLE FOR THE OVERALL UPPER STAGE VERIFICATION AND VALIDATION PROCESS AND WILL REQUIRE SUPPORT FROM THE CONTRACTOR. THE CONTRACTOR IS RESPONSIBLE FOR THE MANUFACTURE AND ASSEMBLY OF THE UPPER STAGE TEST FLIGHT AND OPERATIONAL UPPER STAGE UNITS INCLUDING THE INSTALLATION OF UPPER STAGE INSTRUMENT UNIT, THE GOVERNMENT-FURNISHED US ENGINE, BOOSTER SEPARATION MOTORS, AND OTHER GOVERNMENT-FURNISHED PROPERTY. A DESCRIPTION OF THE NASA MANAGED AND PERFORMED EFFORTS IS CONTAINED IN THE US WORK PACKAGES AND WILL BE MADE AVAILABLE TO THE CONTRACTOR TO ENSURE THEIR UNDERSTANDING OF THE ROLES AND RESPONSIBILITIES OF THE NDT, IUPC, AND CONTRACTOR DURING THE DESIGN, DEVELOPMENT, AND OPERATION OF THE US ELEMENT. THE US CONCEPTUAL DESIGN DESCRIBED IN THE USO-CLV-SE-25704 US DESIGN DEFINITION DOCUMENT (DDD) IS THE BASELINE DESIGN FOR THIS CONTRACT. THE CONTRACTORS EARLY ROLE WILL BE TO PROVIDE PRODUCIBILITY ENGINEERING SUPPORT TO NASA VIA THE ESTABLISHED US OFFICE STRUCTURE AND TO PROVIDE INPUTS INTO THE FINAL DESIGN CONFIGURATION, SPECIFICATIONS, AND STANDARDS. NASA WILL TRANSITION THE MANUFACTURING AND ASSEMBLY, LOGISTICS SUPPORT INFRASTRUCTURE, CONFIGURATION MANAGEMENT, AND THE SUSTAINING ENGINEERING FUNCTIONS TO THE CONTRACTOR AT THE KEY POINTS DURING THE DEVELOPMENT AND IMPLEMENTATION OF THE PROGRAM CURRENTLY PLANNED TO OCCUR NO LATER THAN 90 DAYS AFTER THE COMPLETION OF THE FOLLOWING MAJOR MILESTONES: MANUFACTURING AND ASSEMBLY US PRELIMINARY DESIGN REVIEW (PDR) LOGISTICS SUPPORT INFRASTRUCTURE US PDR CONFIGURATION MANAGEMENT US CRITICAL DESIGN REVIEW CDR) SUSTAINING ENGINEERING US DESIGN CERTIFICATION REVIEW (DCR) AFTER THE COMPLETION OF AN ORDERLY TRANSITION OF ROLES AND RESPONSIBILITIES TO THE CONTRACTOR, NASA WILL ASSUME AN INSIGHT ROLE INTO THE CONTRACTORS PRODUCTION, SUSTAINING ENGINEERING, AND OPERATIONS SUPPORT OF THE ARES I US TEST PROGRAM AND FLIGHT HARDWARE. AFTER DCR, THE CONTRACTOR WILL BE RESPONSIBLE FOR SUSTAINING ENGINEERING PER SOW SECTION 4.7, AS NECESSARY TO MAINTAIN AND SUPPORT THE US CONFIGURATION AND FOR PRODUCTION AND OPERATIONS SUPPORT. — $10.5B
- SPACE LAUNCH SYSTEM (SLS) STAGES PRODUCTION AND EVOLUTION CONTRACT (SPEC) — $2.4B
- INTERIM CRYOGENIC PROPULSION STAGE FOR SLS — $1.3B
- THIS CONTRACT IS TO DESIGN, DEVELOP, FABRICATE, INTEGRATE, TEST, SHIP, PROVIDE LAUNCH SUPPORT, CONDUCT ON-ORBIT CHECKOUT OPERATIONS AND PROVIDE SUSTAINING ENGINEERING SUPPORT FOR TWO TRACKING DATA RELAY SATELLITE (TDRS) SPACECRAFT. THE CONTRACT REQUIREMENTS ALSO INCLUDE THE DESIGN, ASSEMBLE, TEST, INSTALL AND VERIFICATION OF MODIFICATIONS TO THE WHITE SANDS COMPLEX NECESSARY TO MAKE THE GROUND TERMINALS FULLY COMPATIBLE WITH THE TDRS K PROGRAM SPACECRAFT DESIGN. THE CONTRACT ALSO INCLUDES OPTIONS FOR TWO ADDITIONAL SPACECRAFT. — $1.1B
- NASA IS PARTICIPATING WITH THE DOC/NOAA IN A MULTI-SATELLITE PROGRAM TO PROVIDE CONTINUOUS MONITORING OF EARTH AND SPACE ENVIRONMENT PARAMETERS. THE MONITORED PARAMETERS WILL PROVIDE DATA FOR WEATHER PREDICTION MODELS AND PROVIDE SEVERE WEATHER WARNING DATA. THE PROGRAM IS TERMED GEOSTATIONARY OPERATIONAL ENVIRONMENTAL SATELLITE (GOES) AND IS ACCOMPLISHED USING TWO NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA) GEOSTATIONARY SATELLITES STATIONED AT TWO LONGITUDES OVER THE EQUATOR. THE GODDARD SPACE FLIGHT CENTER (GSFC) GOES PROJECT OFFICE HAS BEEN GIVEN RESPONSIBILITY FOR PROCURING THE NECESSARY HARDWARE AND SUPPORT SERVICES TO MEET THE MISSION REQUIREMENTS AS SPECIFIED HEREIN. THE SPACECRAFT CONTRACTOR SHALL FURNISH THE NECESSARY PERSONNEL, FACILITIES, SERVICES, AND MATERIALS TO DESIGN, FABRICATE, INTEGRATE, TEST, DELIVER ON-ORBIT TO NASA, AND SUPPORT ON-ORBIT OPERATIONS FOR ALL OF THE GOES N-Q SPACECRAFT DEVELOPED UNDER THIS CONTRACT. THIS WORK SHALL BE PERFORMED IN ACCORDANCE WITH THE REQUIREMENTS OF THIS DOCUMENT AND ALL ATTACHMENTS TO THE CONTRACT. IN ACCOMPLISHING THE DEVELOPMENT AND DELIVERY OF THE GOES N-Q SPACECRAFT, THE SPACECRAFT CONTRACTOR SHALL PERFORM THE FOLLOWING: 1. PROVIDE THE SPACECRAFT BUS AND THE SPACE ENVIRONMENT MONITOR (SEM) INSTRUMENTS FOR EACH OF THE GOES SPACECRAFT. 2. RECEIVE THE GFE INSTRUMENTS AND RELATED GROUND SUPPORT EQUIPMENT (GSE), THEN INTEGRATE THEM WITH THE SPACECRAFT BUS AND PERFORM SPACECRAFT LEVEL TESTING. 3. PROVIDE ALL REQUIRED SPACECRAFT MECHANICAL AND ELECTRICAL GSE. 4. PROVIDE A SPACECRAFT EMULATOR AND INR PERFORMANCE EVALUATION SYSTEM 5. DELIVER AND SUPPORT INTEGRATION, VERIFICATION, AND MAINTENANCE OF GROUND SYSTEM HARDWARE AND SOFTWARE. 6. DESIGN AND SUPPORT INTEGRATION AND VERIFICATION OF ANY MODIFICATIONS OR REPLACEMENTS TO NOAA GROUND SYSTEM HARDWARE AND SOFTWARE. 7. SUPPORT COMBINED SPACECRAFT AND GROUND SYSTEM TESTING, AND GOES END-TO-END TESTING BEFORE LAUNCH. 8. PROVIDE ALL SERVICES ASSOCIATED WITH THE LAUNCH VEHICLE PROCUREMENT, LAUNCH BASE PROCESSING FACILITY, LAUNCH BASE COORDINATION AND SAFETY, SPACECRAFT/LAUNCH VEHICLE INTEGRATION AND CHECKOUT, AND LAUNCH. 9. PROVIDE ALL SERVICES ASSOCIATED WITH FLIGHT OPERATIONS FROM THE LAUNCH VEHICLE/SPACECRAFT SEPARATION THROUGH SPACECRAFT POSITIONING IN GEOSTATIONARY CHECKOUT ORBIT. 10. SUPPORT ALL SERVICES ASSOCIATED WITH THE ON-ORBIT SPACECRAFT CHECKOUT AND SUPPORT ASSOCIATED WITH INSTRUMENT AND INR CHECKOUT. 11. PROVIDE SPACECRAFT OPERATOR AND ENGINEERING TRAINING FOR ON-ORBIT OPERATION. 12. PROVIDE ON-ORBIT ENGINEERING SUPPORT FOR THE SPACECRAFT SUPPORT GROUND SYSTEM (SSGS) AND EACH SPACECRAFT. THE SPACECRAFT CONTRACTOR IS REQUIRED TO DELIVER THE GOES N-Q SPACECRAFT FULLY COMPATIBLE AND OPERATIONAL WITH NOAA GROUND SYSTEMS: THE SATELLITE OPERATIONS CONTROL CENTER (SOCC), SUITLAND, MD; THE WALLOPS COMMAND AND DATA ACQUISITION STATION (WCDAS), WALLOPS, VA; A BACKUP CDAS; AND THE SPACE ENVIRONMENT CENTER (SEC), BOULDER, CO. CHANGES TO THE EXISTING GROUND SYSTEMS TO ACCOMMODATE UPGRADED OR ADDITIONAL CAPABILITIES ARE PERMITTED AS DEFINED IN SECTION 3.5. THE CONTRACTOR S DELIVERED SPACECRAFT AND ASSOCIATED EFFORTS SHALL MEET ALL REQUIREMENTS OF THE GOES N-Q PERFORMANCE SPECIFICATION. — $584.3M
- IGF::OT::IGF THE COMMERCIAL CREW PROGRAM (CCP) COMMERCIAL CREW TRANSPORTATION CAPABILITY (CCTCAP) CONTRACT WILL PROVIDE COMPLETION OF THE DESIGN, DEVELOPMENT, TEST, EVALUATION, AND CERTIFICATION OF AN INTEGRATED CREW TRANSPORTATION SYSTEM (CTS) CAPABLE OF TRANSPORTING NASA CREW TO AND FROM THE ISS, IN ACCORDANCE WITH THE DESIGN REFERENCE MISSIONS AND NASA'S CERTIFICATION STANDARDS AND REQUIREMENTS. CERTIFICATION OF THE CTS WILL BE DETERMINED BY NASA. NASA PLANS TO ISSUE TASK ORDERS FOR POST CERTIFICATION MISSIONS (PCM) TO AND FROM ISS THAT INCLUDE GROUND, LAUNCH, LIFEBOAT, ON-ORBIT, RETURN AND RECOVERY OPERATIONS. THE MINIMUM QUANTITY OF MISSIONS TO BE ORDERED IS TWO (2) AND THE MAXIMUM POTENTIAL QUANTITY OF MISSIONS WHICH MAY BE ORDERED IS SIX (6). IN ADDITION, NASA MAY ISSUE TASK ORDERS FOR SPECIAL STUDIES USED FOR RISK REDUCTION AND OTHER PURPOSES RELATED TO THE CTS. NASA CERTIFICATION UNDER CLIN 001 IS COMPLETE WHEN THE CONTRACTOR'S CREW TRANSPORTATION SYSTEM (CTS) HAS MET NASA S REQUIREMENTS FOR SAFELY TRANSPORTING CREW TO AND FROM THE INTERNATIONAL SPACE STATION (ISS) IN ACCORDANCE WITH DOCUMENTS IDENTIFIED IN SECTION C.1, SPECIFICATIONS/STATEMENT OF WORK. SUBCLINS 001A AND 001B, IDENTIFIED IN TABLE B.3, DDTE/CERTIFICATION SUBCLINS, ARE DELIVERY MILESTONES THAT REPRESENT COMPLETION OF REQUIRED WORK NECESSARY TO ACHIEVE NASA CERTIFICATION. DELIVERY PAYMENT FOR THE ISS DESIGN CERTIFICATION REVIEW (DCR) FOR THE CREWED FLIGHT TO THE ISS INCLUDES ALL WORK UNDER THIS CLIN THAT OCCURS FROM THE CONTRACT EFFECTIVE DATE THROUGH THE ISS DCR COMPLETION. THE DELIVERY PAYMENT FOR THE CERTIFICATION REVIEW (CR) WILL INCLUDE ALL WORK THAT OCCURS FROMTHE ISS DCR DELIVERY DATE THROUGH THE END OF THE DDTE/CERTIFICATION CLIN 001. IN ACCORDANCE WITH CLAUSE C.1, SPECIFICATION/STATEMENT OF WORK, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTING OFFICER MAY ISSUE POST CERTIFICATION MISSION (PCM) TASK ORDERS. THE CONTRACTOR SHALL USE THE MISSION PRICING RATES SHOWN IN TABLE B.4.1, POST CERTIFICATION MISSION PRICES. THE PER MISSION PRICES ARE FOR A SINGLE ORDER AT THE PRICE STATED PER THE CALENDAR YEAR (CY) BASED ON THE NUMBER OF MISSIONS ORDERED. CTS FULL MISSION CAPABILITY PRICES SHALL BE BASED ON (1) FULFILLMENT OF THE DESIGN REFERENCE MISSION TO THE ISS FOUND IN CCT-DRM-1110, CREW TRANSPORTATION SYSTEM DESIGN REFERENCE MISSIONS, ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, AND OTHER TERMS AND CONDITIONS IN THE CONTRACT AND (2) ALL INHERENT CTS CAPABILITIES THAT ARE WITHIN THE PROPOSED MISSION PRICES. IN ACCORDANCE WITH ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTOR SHALL PERFORM SPECIAL STUDIES, TEST AND ANALYSES, AS INITIATED BY WRITTEN DIRECTION FROM THE CONTRACTING OFFICER. BOEING CCTCAP POST CERTIFICATION MISSION 1 (PCM-1) TASK ORDER AGAINST NNK14MA75C CLIN 002, AS DESCRIBED IN CLAUSE B.4 POST CERTIFICATION MISSIONS (IDIQ)(CLIN 002) AND ALL OTHER APPLICABLE TERMS AND CONDITIONS. — $360.6M
- ORIGINAL AWARD AT GSFC -TRANSFERRED TO KSC 10/1/1998-MEDIUM LIGHT EXPENDABLE LAUNCH VEHICLE (ELV) SERVICES - DOLLARS ADJUSTED UP THRU MOD 68 WHEN TRANSFER OCCURRED — $268.7M
- IGF::OT::IGF THE COMMERCIAL CREW PROGRAM (CCP) COMMERCIAL CREW TRANSPORTATION CAPABILITY (CCTCAP) CONTRACT WILL PROVIDE COMPLETION OF THE DESIGN, DEVELOPMENT, TEST, EVALUATION, AND CERTIFICATION OF AN INTEGRATED CREW TRANSPORTATION SYSTEM (CTS) CAPABLE OF TRANSPORTING NASA CREW TO AND FROM THE ISS, IN ACCORDANCE WITH THE DESIGN REFERENCE MISSIONS AND NASA'S CERTIFICATION STANDARDS AND REQUIREMENTS. CERTIFICATION OF THE CTS WILL BE DETERMINED BY NASA. NASA PLANS TO ISSUE TASK ORDERS FOR POST CERTIFICATION MISSIONS (PCM) TO AND FROM ISS THAT INCLUDE GROUND, LAUNCH, LIFEBOAT, ON-ORBIT, RETURN AND RECOVERY OPERATIONS. THE MINIMUM QUANTITY OF MISSIONS TO BE ORDERED IS TWO (2) AND THE MAXIMUM POTENTIAL QUANTITY OF MISSIONS WHICH MAY BE ORDERED IS SIX (6). IN ADDITION, NASA MAY ISSUE TASK ORDERS FOR SPECIAL STUDIES USED FOR RISK REDUCTION AND OTHER PURPOSES RELATED TO THE CTS. NASA CERTIFICATION UNDER CLIN 001 IS COMPLETE WHEN THE CONTRACTOR'S CREW TRANSPORTATION SYSTEM (CTS) HAS MET NASA'S REQUIREMENTS FOR SAFELY TRANSPORTING CREW TO AND FROM THE INTERNATIONAL SPACE STATION (ISS) IN ACCORDANCE WITH DOCUMENTS IDENTIFIED IN SECTION C.1, SPECIFICATIONS/STATEMENT OF WORK. SUBCLINS 001A AND 001B, IDENTIFIED IN TABLE B.3, DDTE/CERTIFICATION SUBCLINS, ARE DELIVERY MILESTONES THAT REPRESENT COMPLETION OF REQUIRED WORK NECESSARY TO ACHIEVE NASA CERTIFICATION. DELIVERY PAYMENT FOR THE ISS DESIGN CERTIFICATION REVIEW (DCR) FOR THE CREWED FLIGHT TO THE ISS INCLUDES ALL WORK UNDER THIS CLIN THAT OCCURS FROM THE CONTRACT EFFECTIVE DATE THROUGH THE ISS DCR COMPLETION. THE DELIVERY PAYMENT FOR THE CERTIFICATION REVIEW (CR) WILL INCLUDE ALL WORK THAT OCCURS FROMTHE ISS DCR DELIVERY DATE THROUGH THE END OF THE DDTE/CERTIFICATION CLIN 001. IN ACCORDANCE WITH CLAUSE C.1, SPECIFICATION/STATEMENT OF WORK, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTING OFFICER MAY ISSUE POST CERTIFICATION MISSION (PCM) TASK ORDERS. THE CONTRACTOR SHALL USE THE MISSION PRICING RATES SHOWN IN TABLE B.4.1, POST CERTIFICATION MISSION PRICES. THE PER MISSION PRICES ARE FOR A SINGLE ORDER AT THE PRICE STATED PER THE CALENDAR YEAR (CY) BASED ON THE NUMBER OF MISSIONS ORDERED. CTS FULL MISSION CAPABILITY PRICES SHALL BE BASED ON (1) FULFILLMENT OF THE DESIGN REFERENCE MISSION TO THE ISS FOUND IN CCT-DRM-1110, CREW TRANSPORTATION SYSTEM DESIGN REFERENCE MISSIONS, ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, AND OTHER TERMS AND CONDITIONS IN THE CONTRACT AND (2) ALL INHERENT CTS CAPABILITIES THAT ARE WITHIN THE PROPOSED MISSION PRICES. IN ACCORDANCE WITH ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTOR SHALL PERFORM SPECIAL STUDIES, TEST AND ANALYSES, AS INITIATED BY WRITTEN DIRECTION FROM THE CONTRACTING OFFICER. BOEING CCTCAP POST CERTIFICATION MISSION 2 (PCM-2) TASK ORDER AGAINST NNK14MA75C CLIN 002, AS DESCRIBED IN CLAUSE B.4 POST CERTIFICATION MISSIONS (IDIQ)(CLIN 002) AND ALL OTHER APPLICABLE TERMS AND CONDITIONS. — $254.3M
- ARES I UPPER STAGE INSTRUMENT UNIT AVIONICS DEVELOPMENT. THE UPPER STAGE (US) ELEMENT IS AN INTEGRAL PART OF THE ARES I LAUNCH VEHICLE AND PROVIDES THE SECOND STAGE OF FLIGHT. THE US ES RESPONSIBLE FOR THE ROLL CONTROL DURING THE FIRST STAGE BURN AND SEPARATION AND WILL PROVIDE THE GUIDANCE AND NAVIGATION, COMMAND AND DATA HANDLING, AND OTHER AVIONICS FUNCTIONS FOR THE ARES I DURING ALL PHASES OF THE ASCENT FLIGHT. THE US IS A NEW DESIGN THAT EMPHASIZES SAFETY, OPERABILITY, AND MINIMUM LIFE-CYCLE COST. THE OVERALL DESIGN, DEVELOPMENT, TEST AND EVALUATION (DDT&E), PRODUCTION, AND SUSTAINING ENGINEERING EFFORTS INCLUDE ACTIVITIES PERFORMED BY THREE ORGANIZATIONS: THE NASA DESIGN TEAM (NDT), THE UPPER STAGE PRODUCTION CONTRACTOR (USPC) AND THE INSTRUMENT UNIT AVIONICS CONTRACTOR (IUAC). THE USPC WAS SELECTED VIA A SEPARATE ACQUISITION. NASA IS RESPONSIBLE FOR THE INTEGRATION OF THE PRIMARY ELEMENTS OF THE ARES I LAUNCH VEHICLE INCLUDING: THE FIRST STAGE, US INCLUDING INSTRUMENT UNIT (IU), US ENGINE, AND ORION AND WILL ALSO INTEGRATE THE ARES I LAUNCH VEHICLE AT THE LAUNCH SITE. THE US AVIONICS HARDWARE AND SOFTWARE SYSTEM ARCHITECTURE AND SPECIFICATIONS WILL BE DEVELOPED BY THE NASA MARSHALL SPACE FLIGHT CENTER (MSFC) LED TEAM, IN CONJUNCTION WITH GLENN RESEARCH CENTER (GRC), AMES RESEARCH CENTER (ARC), AND KENNEDY SPACE CENTER (KSC). THE NDT IS COMPOSED OF BOTH GOVERNMENT CIVIL SERVANTS AND SUPPORT CONTRACTORS FROM EACH OF THE AFOREMENTIONED CENTERS. THE NDTS AVIONICS AND SOFTWARE DEVELOPMENT APPROACH IS DOCUMENTED IN USO-CLV-DE-25106, UPPER STAGE AVIONICS DEVELOPMENT PLAN. THE INSTRUMENT UNIT (IU) WILL HOUSE THE MAJORITY OF THE ARES I US AVIONICS. A SMALLER SET OF ELECTRONICS AND CABLE HARNESSES WILL BE LOCATED ON THE US CORE STRUCTURE AND INTERSTAGE STRUCTURE. THE US CONCEPTUAL DESIGN DESCRIBED IN THE USO-CLV-SE-25704 US DESIGN DEFINITION DOCUMENT (DDD) IS THE BASELINE VEHICLE DESIGN. THE ARES I US AVIONICS AND SOFTWARE SUBSYSTEM SPECIFICATION (USO-CLV-DE-25107), THE ELECTRICAL GROUND SUPPORT EQUIPMENT (EGSE) SUBSYSTEM REQUIREMENTS SPECIFICATION (USO-CLV-DE-25135), AND THE ARES I US AVIONICS AND SOFTWARE COMPONENT END ITEM (CEI) SPECIFICATIONS (USO-CLV-DE-25107), LISTED IN SECTION 5, WILL SERVE AS THE SOURCE FOR TECHNICAL REQUIREMENTS FOR THE CONTRACTOR. THIS IS A COST PLUS AWARD FEE (CPAF) TYPE OF CONTRACT AND FEE FOR CLINS 1 AND 2 IS EARNED BASED ON THE AWARD FEE SCORE GIVEN AT THE END OF EACH AWARD FEE PERIOD. FEE FOR CLINS 1 AND 2 ARE EVALUATED UNDER NASA FAR SUPPLEMENT (NFS) CLAUSE 1852.216-76, AWARD FEE FOR SERVICE CONTRACTS. THE AMOUNT OF AVAILABLE AWARD FEE SHOWN IN TABLE 3 OF PARAGRAPH 1.4, BELOW, IS SUBJECT TO ADJUSTMENT BASED ON IDIQ WORK AUTHORIZED UNDER CLIN 2. ADDITIONALLY, THE AMOUNT OF AVAILABLE AWARD FEE IN EACH PERIOD IS SUBJECT TO EQUITABLE ADJUSTMENTS ARISING FROM CHANGES OR OTHER CONTRACT MODIFICATIONS. — $196.3M
- 4200001394 1F TECHNOLOGY AREA 10-FLIGHT DEMONSTRATION RISK REDUCTION — $195.1M
- OVERALL PAYLOAD INTEGRATION FOR ISS PAYLOAD — $184.0M
- IGF::OT::IGF THE COMMERCIAL CREW PROGRAM (CCP) COMMERCIAL CREW TRANSPORTATION CAPABILITY (CCTCAP) CONTRACT WILL PROVIDE COMPLETION OF THE DESIGN, DEVELOPMENT, TEST, EVALUATION, AND CERTIFICATION OF AN INTEGRATED CREW TRANSPORTATION SYSTEM (CTS) CAPABLE OF TRANSPORTING NASA CREW TO AND FROM THE ISS, IN ACCORDANCE WITH THE DESIGN REFERENCE MISSIONS AND NASA'S CERTIFICATION STANDARDS AND REQUIREMENTS. CERTIFICATION OF THE CTS WILL BE DETERMINED BY NASA. NASA PLANS TO ISSUE TASK ORDERS FOR POST CERTIFICATION MISSIONS (PCM) TO AND FROM ISS THAT INCLUDE GROUND, LAUNCH, LIFEBOAT, ON-ORBIT, RETURN AND RECOVERY OPERATIONS. THE MINIMUM QUANTITY OF MISSIONS TO BE ORDERED IS TWO (2) AND THE MAXIMUM POTENTIAL QUANTITY OF MISSIONS WHICH MAY BE ORDERED IS SIX (6). IN ADDITION, NASA MAY ISSUE TASK ORDERS FOR SPECIAL STUDIES USED FOR RISK REDUCTION AND OTHER PURPOSES RELATED TO THE CTS. NASA CERTIFICATION UNDER CLIN 001 IS COMPLETE WHEN THE CONTRACTOR'S CREW TRANSPORTATION SYSTEM (CTS) HAS MET NASAS REQUIREMENTS FOR SAFELY TRANSPORTING CREW TO AND FROM THE INTERNATIONAL SPACE STATION (ISS) IN ACCORDANCE WITH DOCUMENTS IDENTIFIED IN SECTION C.1, SPECIFICATIONS/STATEMENT OF WORK. SUBCLINS 001A AND 001B, IDENTIFIED IN TABLE B.3, DDTE/CERTIFICATION SUBCLINS, ARE DELIVERY MILESTONES THAT REPRESENT COMPLETION OF REQUIRED WORK NECESSARY TO ACHIEVE NASA CERTIFICATION. DELIVERY PAYMENT FOR THE ISS DESIGN CERTIFICATION REVIEW (DCR) FOR THE CREWED FLIGHT TO THE ISS INCLUDES ALL WORK UNDER THIS CLIN THAT OCCURS FROM THE CONTRACT EFFECTIVE DATE THROUGH THE ISS DCR COMPLETION. THE DELIVERY PAYMENT FOR THE CERTIFICATION REVIEW (CR) WILL INCLUDE ALL WORK THAT OCCURS FROM THE ISS DCR DELIVERY DATE THROUGH THE END OF THE DDTE/CERTIFICATION CLIN 001. IN ACCORDANCE WITH CLAUSE C.1, SPECIFICATION/STATEMENT OF WORK, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTING OFFICER MAY ISSUE POST CERTIFICATION MISSION (PCM) TASK ORDERS. THE CONTRACTOR SHALL USE THE MISSION PRICING RATES SHOWN IN TABLE B.4.1, POST CERTIFICATION MISSION PRICES. THE PER MISSION PRICES ARE FOR A SINGLE ORDER AT THE PRICE STATED PER THE CALENDAR YEAR (CY) BASED ON THE NUMBER OF MISSIONS ORDERED. CTS FULL MISSION CAPABILITY PRICES SHALL BE BASED ON (1) FULFILLMENT OF THE DESIGN REFERENCE MISSION TO THE ISS FOUND IN CCT-DRM-1110, CREW TRANSPORTATION SYSTEM DESIGN REFERENCE MISSIONS, ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, AND OTHER TERMS AND CONDITIONS IN THE CONTRACT AND (2) ALL INHERENT CTS CAPABILITIES THAT ARE WITHIN THE PROPOSED MISSION PRICES. IN ACCORDANCE WITH ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTOR SHALL PERFORM SPECIAL STUDIES, TEST AND ANALYSES, AS INITIATED BY WRITTEN DIRECTION FROM THE CONTRACTING OFFICER. BOEING CCTCAP POST CERTIFICATION MISSION 3-6 (PCM-3-6) TASK ORDER AGAINST NNK14MA75C CLIN 002, AS DESCRIBED IN CLAUSE B.4 POST CERTIFICATION MISSIONS (IDIQ)(CLIN 002) AND ALL OTHER APPLICABLE TERMS AND CONDITIONS. — $178.1M
- CONTRACT WITH THE BOEING COMPANY TO PROVIDE 40 REPLACEMENT BATTERY ORBITAL REPLACEMENT UNITS (ORUS) FOR ISS — $145.2M
- ORIGINAL AWARD AT GSFC- TRANSFERRED TO KSC 10/1/1998 FOR LAUNCH OF MEDIUM CLASS EXPENDABLE LAUNCH VEHICLES(ELVS)W/GOVT PAYLOADS INTO ASSIGNED ORBIT(S)-TOTALS ADJUSTED UP THRU MOD 288 WHEN TRANSFERRED FROM GSFC — $145.1M
- ENVIRONMENTAL REMEDIATION SERVICES, SANTA SUSANA FIELD LABORATORY — $33.1M
- THIS CONTRACT IS FOR THE DESIGN AND FABRICATION OF RADIATION HARDENED CHIPLET DEVICES — $30.5M
- IGF::OT::IGF THE COMMERCIAL CREW PROGRAM (CCP) COMMERCIAL CREW TRANSPORTATION CAPABILITY (CCTCAP) CONTRACT WILL PROVIDE COMPLETION OF THE DESIGN, DEVELOPMENT, TEST, EVALUATION, AND CERTIFICATION OF AN INTEGRATED CREW TRANSPORTATION SYSTEM (CTS) CAPABLE OF TRANSPORTING NASA CREW TO AND FROM THE ISS, IN ACCORDANCE WITH THE DESIGN REFERENCE MISSIONS AND NASA'S CERTIFICATION STANDARDS AND REQUIREMENTS. CERTIFICATION OF THE CTS WILL BE DETERMINED BY NASA. NASA PLANS TO ISSUE TASK ORDERS FOR POST CERTIFICATION MISSIONS (PCM) TO AND FROM ISS THAT INCLUDE GROUND, LAUNCH, LIFEBOAT, ON-ORBIT, RETURN AND RECOVERY OPERATIONS. THE MINIMUM QUANTITY OF MISSIONS TO BE ORDERED IS TWO (2) AND THE MAXIMUM POTENTIAL QUANTITY OF MISSIONS WHICH MAY BE ORDERED IS SIX (6). IN ADDITION, NASA MAY ISSUE TASK ORDERS FOR SPECIAL STUDIES USED FOR RISK REDUCTION AND OTHER PURPOSES RELATED TO THE CTS. NASA CERTIFICATION UNDER CLIN 001 IS COMPLETE WHEN THE CONTRACTOR'S CREW TRANSPORTATION SYSTEM (CTS) HAS MET NASA'S REQUIREMENTS FOR SAFELY TRANSPORTING CREW TO AND FROM THE INTERNATIONAL SPACE STATION (ISS) IN ACCORDANCE WITH DOCUMENTS IDENTIFIED IN SECTION C.1, SPECIFICATIONS/STATEMENT OF WORK. SUBCLINS 001A AND 001B, IDENTIFIED IN TABLE B.3, DDTE/CERTIFICATION SUBCLINS, ARE DELIVERY MILESTONES THAT REPRESENT COMPLETION OF REQUIRED WORK NECESSARY TO ACHIEVE NASA CERTIFICATION. DELIVERY PAYMENT FOR THE ISS DESIGN CERTIFICATION REVIEW (DCR) FOR THE CREWED FLIGHT TO THE ISS INCLUDES ALL WORK UNDER THIS CLIN THAT OCCURS FROM THE CONTRACT EFFECTIVE DATE THROUGH THE ISS DCR COMPLETION. THE DELIVERY PAYMENT FOR THE CERTIFICATION REVIEW (CR) WILL INCLUDE ALL WORK THAT OCCURS FROM THE ISS DCR DELIVERY DATE THROUGH THE END OF THE DDTE/CERTIFICATION CLIN 001. IN ACCORDANCE WITH CLAUSE C.1, SPECIFICATION/STATEMENT OF WORK, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTING OFFICER MAY ISSUE POST CERTIFICATION MISSION (PCM) TASK ORDERS. THE CONTRACTOR SHALL USE THE MISSION PRICING RATES SHOWN IN TABLE B.4.1, POST CERTIFICATION MISSION PRICES. THE PER MISSION PRICES ARE FOR A SINGLE ORDER AT THE PRICE STATED PER THE CALENDAR YEAR (CY) BASED ON THE NUMBER OF MISSIONS ORDERED. CTS FULL MISSION CAPABILITY PRICES SHALL BE BASED ON (1) FULFILLMENT OF THE DESIGN REFERENCE MISSION TO THE ISS FOUND IN CCT-DRM-1110, CREW TRANSPORTATION SYSTEM DESIGN REFERENCE MISSIONS, ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, AND OTHER TERMS AND CONDITIONS IN THE CONTRACT AND (2) ALL INHERENT CTS CAPABILITIES THAT ARE WITHIN THE PROPOSED MISSION PRICES. IN ACCORDANCE WITH ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTOR SHALL PERFORM SPECIAL STUDIES, TEST AND ANALYSES, AS INITIATED BY WRITTEN DIRECTION FROM THE CONTRACTING OFFICER. — $27.1M
- COMPOSITE CRYOGENIC TECHNOLOGIES AND DEMONSTRATION (CCTD) TASK ORDER — $26.3M
- IGF::OT::IGF BAA - NEXT SPACE TECHNOLOGIES FOR EXPLORATION PARTNERSHIPS (NEXTSTEP) PROPOSAL - HABITATION. NASA HAS INCREASINGLY EMBRACED PUBLIC-PRIVATE PARTNERSHIPS FOR ACHIEVING ITS STRATEGIC GOALS AND OBJECTIVES FOR EXPANDING THE FRONTIERS OF KNOWLEDGE, CAPABILITY, AND OPPORTUNITIES IN SPACE. THE NEXT STEP FOR HUMAN SPACEFLIGHT IS THE DEVELOPMENT OF DEEP SPACE EXPLORATION CAPABILITIES TO SUPPORT MORE EXTENSIVE MISSIONS IN THE PROVING GROUND AROUND AND BEYOND CISLUNAR SPACE. AN IMPORTANT PART OF NASAS STRATEGY IS TO STIMULATE THE COMMERCIAL SPACE INDUSTRY WHILE LEVERAGING THOSE SAME COMMERCIAL CAPABILITIES THROUGH FUTURE CONTRACTS AND PUBLIC-PRIVATE PARTNERSHIPS TO DELIVER MISSION CAPABILITIES. NASAS ACTIVITIES IN ENABLING THE PIONEERING OF SPACE ARE BEING DRIVEN BY A SET OF GUIDING PRINCIPLES: IMPLEMENTABLE IN THE NEAR-TERM WITH THE BUYING POWER OF CURRENT BUDGETS AND IN THE LONGER TERM WITH BUDGETS COMMENSURATE WITH ECONOMIC GROWTH; EXPLORATION ENABLES SCIENCE AND SCIENCE ENABLES EXPLORATION APPLICATION OF HIGH TECHNOLOGY READINESS LEVEL (TRL) TECHNOLOGIES FOR NEAR TERM MISSIONS, WHILE FOCUSING SUSTAINED INVESTMENTS ON TECHNOLOGIES AND CAPABILITIES TO ADDRESS CHALLENGES OF FUTURE MISSIONS; NEAR-TERM MISSION OPPORTUNITIES WITH A DEFINED CADENCE OF COMPELLING AND INTEGRATED HUMAN AND ROBOTIC MISSIONS PROVIDING FOR AN INCREMENTAL BUILDUP OF CAPABILITIES FOR MORE COMPLEX MISSIONS OVER TIME; OPPORTUNITIES FOR U.S. COMMERCIAL BUSINESS TO FURTHER ENHANCE THE EXPERIENCE AND BUSINESS BASE MULTI-USE, EVOLVABLE SPACE INFRASTRUCTURE, MINIMIZING UNIQUE MAJOR DEVELOPMENTS; SUBSTANTIAL INTERNATIONAL AND COMMERCIAL PARTICIPATION, LEVERAGING CURRENT INTERNATIONAL SPACE STATION AND OTHER PARTNERSHIPS. THE CONTRACTOR SHALL DEVELOP A SIMPLE, LOW COST EXPLORATION AUGMENTATION MODULE (EAM) THAT IS AFFORDABLE EARLY ON, THAT ALLOWS VARIOUS TECHNOLOGIES TO BE TESTED OVER TIME, AND THAT IS CAPABLE OF EVOLVING INTO A LONG-DURATION CREW SUPPORT SYSTEM FOR CISLUNAR AND MARS EXPLORATION. — $25.7M
Frequently Asked Questions
How many contracts does THE Boeing Company have with National Aeronautics and Space Administration?
THE Boeing Company has 26 contracts with National Aeronautics and Space Administration worth a combined $40.4B.
What is the average contract size between THE Boeing Company and National Aeronautics and Space Administration?
The average contract size is $1.6B.
What percentage of THE Boeing Company's contracts with National Aeronautics and Space Administration are sole-source?
0% of the contracts are sole-source awards.