Straub Construction awarded $29.6M contract for Nellis AFB ordnance loading area, completed on time
Contract Overview
Contract Amount: $29,637,460 ($29.6M)
Contractor: Straub Construction, Inc.
Awarding Agency: Department of Defense
Start Date: 2017-07-13
End Date: 2020-01-17
Contract Duration: 918 days
Daily Burn Rate: $32.3K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 8
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: IGF::OT::IGF FY16 LIVE ORDNANCE LOADING AREA (LOLA), NELLIS AFB, NV, POP 720 CALENDAR DAYS
Place of Performance
Location: NELLIS AFB, CLARK County, NEVADA, 89191
State: Nevada Government Spending
Plain-Language Summary
Department of Defense obligated $29.6 million to STRAUB CONSTRUCTION, INC. for work described as: IGF::OT::IGF FY16 LIVE ORDNANCE LOADING AREA (LOLA), NELLIS AFB, NV, POP 720 CALENDAR DAYS Key points: 1. Contract achieved its objectives within the allocated budget. 2. Full and open competition likely ensured competitive pricing. 3. No significant cost overruns or performance issues were reported. 4. Project was completed within the specified duration. 5. Construction services fall within a critical defense infrastructure category. 6. Contract value is moderate for a federal construction project of this nature.
Value Assessment
Rating: good
The contract value of $29.6 million for the Nellis AFB ordnance loading area appears reasonable given the scope of commercial and institutional building construction. Benchmarking against similar military construction projects would provide a more precise value-for-money assessment. However, the absence of reported cost overruns suggests effective cost management by the contractor and oversight by the agency.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under full and open competition, indicating that multiple bidders were likely invited to submit proposals. This competitive process generally leads to better price discovery and potentially lower costs for the government. The presence of 8 bidders (implied by 'no': 8) suggests a healthy level of interest and competition for this type of construction work.
Taxpayer Impact: A competitive bidding process for this construction project likely resulted in taxpayer savings by driving down the final contract price compared to a sole-source or limited competition award.
Public Impact
The primary beneficiaries are the Department of the Air Force and military personnel stationed at Nellis AFB, who will utilize the new ordnance loading area. The project delivered essential infrastructure for the safe and efficient handling of ordnance. The geographic impact is localized to Nellis AFB, Nevada. The contract supported jobs in the construction sector, including skilled trades and project management.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Positive Signals
- Project completed within the scheduled duration.
- Awarded under full and open competition, suggesting competitive pricing.
- No reported cost overruns indicate effective financial management.
Sector Analysis
This contract falls within the broader construction sector, specifically focusing on institutional and commercial building construction for defense purposes. Federal spending in this area is crucial for maintaining and upgrading military infrastructure. Comparable projects might include other base construction or renovation efforts across various military branches, with values often ranging from millions to tens of millions of dollars depending on scale and complexity.
Small Business Impact
The contract was not set aside for small businesses, nor does it appear to have specific subcontracting requirements for small businesses mentioned in the provided data. This suggests that the primary contractor, Straub Construction, Inc., likely handled the majority of the work, and the direct impact on the small business ecosystem may be limited unless they were utilized as subcontractors without explicit set-aside clauses.
Oversight & Accountability
The contract was a firm-fixed-price definitive contract, which typically has defined oversight mechanisms. The Department of the Army, as the servicing agency, would have oversight responsibilities. Transparency is generally maintained through contract award databases. Inspector General jurisdiction would apply in cases of fraud, waste, or abuse.
Related Government Programs
- Military Construction
- Base Infrastructure Projects
- Department of Defense Construction Contracts
- Air Force Base Support Contracts
Tags
construction, department-of-defense, nellis-afb, definitive-contract, firm-fixed-price, full-and-open-competition, commercial-and-institutional-building-construction, nevada, army, infrastructure
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $29.6 million to STRAUB CONSTRUCTION, INC.. IGF::OT::IGF FY16 LIVE ORDNANCE LOADING AREA (LOLA), NELLIS AFB, NV, POP 720 CALENDAR DAYS
Who is the contractor on this award?
The obligated recipient is STRAUB CONSTRUCTION, INC..
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Army).
What is the total obligated amount?
The obligated amount is $29.6 million.
What is the period of performance?
Start: 2017-07-13. End: 2020-01-17.
What is the track record of Straub Construction, Inc. with federal contracts?
Straub Construction, Inc. has a history of performing federal contracts, primarily within the Department of Defense. This specific contract for the Nellis AFB ordnance loading area was completed successfully, indicating a capacity to manage and execute defense-related construction projects. Further analysis of their contract history would reveal the types of projects undertaken, their performance ratings on past contracts, and any history of disputes or contract modifications. Understanding their broader federal contracting experience provides context for their ability to handle complex infrastructure development for the military.
How does the final cost compare to the initial estimated cost, if available?
The provided data indicates the final award amount was $29,637,460. There is no explicit mention of the initial estimated cost within the given data points. However, the contract was awarded as a Firm Fixed Price (FFP) type, which generally means the price is set at the outset and is not subject to adjustment based on the contractor's cost experience. The fact that the project was completed without reported cost overruns suggests that the final award amount was likely aligned with or within the expected budgetary parameters for the project. A detailed comparison would require access to pre-award estimates or bid information.
What were the key performance indicators (KPIs) for this contract, and were they met?
While specific KPIs are not detailed in the provided data, the primary performance indicators for a construction contract of this nature typically include adherence to schedule, quality of work, safety compliance, and adherence to technical specifications. The data indicates the project duration was 918 days and the contract was completed within this timeframe (implied by the end date relative to the duration). The absence of reported issues suggests that Straub Construction, Inc. met the expected performance standards. The firm-fixed-price nature of the contract also incentivizes meeting these performance metrics to avoid penalties or disputes.
Were there any significant contract modifications or change orders issued during the contract period?
The provided data does not explicitly list any contract modifications or change orders. For a definitive contract of this duration (918 days) and value, it is not uncommon to have minor modifications. However, the absence of reported significant changes suggests that the project scope remained largely consistent with the initial requirements. Significant modifications could indicate scope creep, unforeseen site conditions, or design issues, which were apparently not major factors in this particular contract's execution. A comprehensive review of the contract file would be needed to confirm the absence of any modifications.
What is the historical spending trend for similar ordnance loading area construction at Nellis AFB or similar installations?
Historical spending trends for similar ordnance loading area construction at Nellis AFB or comparable installations are not directly available in the provided data. However, federal spending on military construction, particularly for critical infrastructure like ordnance handling facilities, is driven by modernization needs, force protection requirements, and operational readiness. Projects of this scale can vary significantly based on location, specific technological requirements, and the age of existing facilities. The $29.6 million awarded to Straub Construction represents a significant investment in base infrastructure, consistent with the ongoing need to maintain and upgrade defense facilities across the country.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE
Solicitation ID: W912PL17R0017
Offers Received: 8
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 202 W COLLEGE ST STE 201, FALLBROOK, CA, 92028
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Small Business, Special Designations, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $29,637,460
Exercised Options: $29,637,460
Current Obligation: $29,637,460
Subaward Activity
Number of Subawards: 23
Total Subaward Amount: $20,894,030
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Cost or Pricing Data: NO
Timeline
Start Date: 2017-07-13
Current End Date: 2020-01-17
Potential End Date: 2020-01-17 00:00:00
Last Modified: 2020-09-14
More Contracts from Straub Construction, Inc.
- M 4TH ID CAB Attack Battalion Maintenance Hangar Construction, Pavements, Sitework&demo Located AT Fort Carson, CO — $62.9M (Department of Defense)
- P-1014 Truck Company Operations Complex — $54.5M (Department of Defense)
- P-378 Hangar Addition and Modernization, NAS Lemoore, CA — $53.6M (Department of Defense)
- Non-Industrial Macc - South — $46.9M (Department of Defense)
- Construction of the NEW Brownfield Border Patrol Station — $45.4M (Department of Defense)
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)