Army Awards $29.8M Canton Dam Spillway Contract to Kiewit Infrastructure South

Contract Overview

Contract Amount: $29,834,565 ($29.8M)

Contractor: Kiewit Infrastructure South CO

Awarding Agency: Department of Defense

Start Date: 2014-08-26

End Date: 2016-12-01

Contract Duration: 828 days

Daily Burn Rate: $36.0K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 6

Pricing Type: FIRM FIXED PRICE

Sector: Construction

Official Description: IGF::OT::IGF DESIGN-BID-BUILD AUXILIARY SPILLWAY AT CANTON DAM, CANTON, OKLAHOMA.

Place of Performance

Location: CANTON, BLAINE County, OKLAHOMA, 73724

State: Oklahoma Government Spending

Plain-Language Summary

Department of Defense obligated $29.8 million to KIEWIT INFRASTRUCTURE SOUTH CO for work described as: IGF::OT::IGF DESIGN-BID-BUILD AUXILIARY SPILLWAY AT CANTON DAM, CANTON, OKLAHOMA. Key points: 1. Contract awarded for auxiliary spillway construction at Canton Dam, Oklahoma. 2. Kiewit Infrastructure South secured the $29.8 million contract. 3. The project falls under heavy and civil engineering construction. 4. Full and open competition was utilized for this award.

Value Assessment

Rating: good

The contract value of $29.8 million appears reasonable for a project of this scope, involving significant civil engineering and construction. Benchmarking against similar dam and spillway construction projects would provide a more precise assessment.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The contract was awarded under full and open competition, suggesting a robust process for soliciting bids and ensuring competitive pricing. This method generally leads to better price discovery and value for the government.

Taxpayer Impact: Full and open competition likely resulted in a fair market price, maximizing taxpayer value for the construction of critical infrastructure.

Public Impact

Enhances dam safety and flood control capabilities for the Canton Dam region. Supports local economy through construction jobs and related services. Represents federal investment in vital water infrastructure management.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Positive Signals

Sector Analysis

This contract falls within the heavy and civil engineering construction sector, which is crucial for maintaining and upgrading public infrastructure. Spending in this sector can vary significantly based on federal infrastructure initiatives and regional needs.

Small Business Impact

The data indicates no specific set-aside for small businesses for this contract. While Kiewit is a large contractor, subcontracting opportunities may exist for smaller firms within the construction trades.

Oversight & Accountability

The contract was awarded by the Department of the Army, implying oversight through established federal procurement regulations. Further oversight would involve project management and quality assurance during construction.

Related Government Programs

Risk Flags

Tags

other-heavy-and-civil-engineering-constr, department-of-defense, ok, definitive-contract, 10m-plus

Frequently Asked Questions

What is this federal contract paying for?

Department of Defense awarded $29.8 million to KIEWIT INFRASTRUCTURE SOUTH CO. IGF::OT::IGF DESIGN-BID-BUILD AUXILIARY SPILLWAY AT CANTON DAM, CANTON, OKLAHOMA.

Who is the contractor on this award?

The obligated recipient is KIEWIT INFRASTRUCTURE SOUTH CO.

Which agency awarded this contract?

Awarding agency: Department of Defense (Department of the Army).

What is the total obligated amount?

The obligated amount is $29.8 million.

What is the period of performance?

Start: 2014-08-26. End: 2016-12-01.

What was the competitive landscape like for this bid, and did the winning bid significantly undercut other proposals?

The contract was awarded under full and open competition, indicating multiple bids were likely received. While the specific bid amounts of competitors are not provided, the use of this procurement method suggests a competitive process aimed at achieving the best value. Further analysis of the bid tabulation would reveal the extent of price differentiation among bidders.

Are there any potential risks associated with the contractor's past performance or the project's complexity?

Kiewit Infrastructure South is a large, established construction firm with a history of undertaking significant infrastructure projects. While specific performance issues are not detailed here, risks could include potential construction delays, cost overruns if unforeseen site conditions arise, or challenges in coordinating with local stakeholders. A review of Kiewit's performance on similar projects would offer more insight.

How does the final cost compare to initial estimates or industry benchmarks for similar spillway construction?

Without initial cost estimates or detailed project specifications, a direct comparison is difficult. However, the $29.8 million award for an auxiliary spillway at Canton Dam appears to be a substantial investment. Benchmarking against similar-sized dam improvement projects in comparable geographic regions would be necessary to assess if the cost is within expected parameters.

Industry Classification

NAICS: ConstructionOther Heavy and Civil Engineering ConstructionOther Heavy and Civil Engineering Construction

Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIESCONSTRUCTION OF BUILDINGS

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE

Solicitation ID: W912BV14R0039

Offers Received: 6

Pricing Type: FIRM FIXED PRICE (J)

Evaluated Preference: NONE

Contractor Details

Parent Company: Peter Kiewit Sons Inc (UEI: 070729517)

Address: KIEWIT PLZ NO 1044, OMAHA, NE, 68131

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, U.S.-Owned Business

Financial Breakdown

Contract Ceiling: $31,414,321

Exercised Options: $29,834,565

Current Obligation: $29,834,565

Contract Characteristics

Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED

Cost or Pricing Data: NO

Timeline

Start Date: 2014-08-26

Current End Date: 2016-12-01

Potential End Date: 2016-12-01 00:00:00

Last Modified: 2017-09-08

More Contracts from Kiewit Infrastructure South CO

View all Kiewit Infrastructure South CO federal contracts →

Other Department of Defense Contracts

View all Department of Defense contracts →

Explore Related Government Spending