Contract Overview

Contract Amount: $163,799,711 ($163.8M)

Contractor: Voith Hydro Inc

Awarding Agency: Department of Defense

Start Date: 2021-12-15

End Date: 2032-09-27

Contract Duration: 3,939 days

Daily Burn Rate: $41.6K/day

Competition Type: FULL AND OPEN COMPETITION

Number of Offers Received: 3

Pricing Type: FIRM FIXED PRICE

Sector: Construction

Official Description: E.O.14042 FORT RANDALL MAJOR UNIT REHABILITATION

Place of Performance

Location: PICKSTOWN, CHARLES MIX County, SOUTH DAKOTA, 57367

State: South Dakota Government Spending

Plain-Language Summary

Department of Defense obligated $163.8 million to VOITH HYDRO INC for work described as: E.O.14042 FORT RANDALL MAJOR UNIT REHABILITATION Key points: 1. Significant investment in critical infrastructure, potentially boosting regional economic activity. 2. Voith Hydro Inc. secured a large contract, indicating strong capabilities in heavy civil engineering. 3. Long contract duration (2032) presents potential for cost overruns or scope creep. 4. Focus on rehabilitation suggests aging infrastructure needs, a common challenge across government sectors.

Value Assessment

Rating: fair

The contract value of $163.8M for a major unit rehabilitation is substantial. Benchmarking against similar large-scale civil engineering projects is difficult without more specific scope details, but the price appears within a reasonable range for the complexity and duration.

Cost Per Unit: N/A

Competition Analysis

Competition Level: full-and-open

The contract was awarded under full and open competition, suggesting a robust price discovery process. This method typically leads to more competitive pricing by allowing all qualified vendors to bid.

Taxpayer Impact: Taxpayer funds are being used for essential infrastructure upgrades, aiming for long-term reliability and potentially avoiding more costly emergency repairs later.

Public Impact

Ensures continued operation of a critical energy infrastructure component. Supports jobs in the construction and engineering sectors in South Dakota. Addresses aging infrastructure, enhancing national energy security and reliability.

Waste & Efficiency Indicators

Waste Risk Score: 50 / 10

Warning Flags

Positive Signals

Sector Analysis

This contract falls within the heavy and civil engineering construction sector, which often involves large, complex projects with long timelines. Spending benchmarks for dam rehabilitation vary widely based on specific components and scale.

Small Business Impact

While the primary award went to Voith Hydro Inc., the nature of large-scale civil engineering projects often involves significant subcontracting opportunities. It's unclear from this data if small businesses were specifically targeted or utilized in the bidding process.

Oversight & Accountability

The Department of the Army, through its contracting arm, is responsible for oversight. The long duration necessitates diligent monitoring of progress, quality, and adherence to the firm fixed price to ensure accountability.

Related Government Programs

Risk Flags

Tags

other-heavy-and-civil-engineering-constr, department-of-defense, sd, definitive-contract, 100m-plus

Frequently Asked Questions

What is this federal contract paying for?

Department of Defense awarded $163.8 million to VOITH HYDRO INC. E.O.14042 FORT RANDALL MAJOR UNIT REHABILITATION

Who is the contractor on this award?

The obligated recipient is VOITH HYDRO INC.

Which agency awarded this contract?

Awarding agency: Department of Defense (Department of the Army).

What is the total obligated amount?

The obligated amount is $163.8 million.

What is the period of performance?

Start: 2021-12-15. End: 2032-09-27.

What specific components of the Fort Randall Dam are included in this rehabilitation, and how does this scope compare to similar projects?

The provided data lacks specific details on the rehabilitation scope beyond 'major unit rehabilitation.' A comprehensive comparison to similar projects would require a detailed breakdown of the work, such as turbine, generator, or spillway repairs, and the specific condition assessments that informed the project's requirements and cost.

What are the key performance indicators (KPIs) and risk mitigation strategies in place for this decade-long contract?

Given the 2032 completion date, robust KPIs for performance, quality, and safety are crucial. Risk mitigation strategies should address potential supply chain disruptions, labor availability, inflation, and unforeseen geological or structural issues inherent in aging infrastructure projects.

How will the effectiveness of this rehabilitation be measured post-completion to ensure long-term value for taxpayers?

Effectiveness will likely be measured by the dam's restored operational capacity, improved efficiency, reduced maintenance needs, and enhanced safety and reliability. Post-completion assessments and ongoing performance monitoring against baseline metrics will be key to verifying long-term value.

Industry Classification

NAICS: ConstructionOther Heavy and Civil Engineering ConstructionOther Heavy and Civil Engineering Construction

Product/Service Code: MAINT, REPAIR, ALTER REAL PROPERTYMAINT, ALTER, REPAIR NONBUILDINGS

Competition & Pricing

Extent Competed: FULL AND OPEN COMPETITION

Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE

Solicitation ID: W9128F21R0005

Offers Received: 3

Pricing Type: FIRM FIXED PRICE (J)

Evaluated Preference: NONE

Contractor Details

Address: 760 E BERLIN RD, YORK, PA, 17408

Business Categories: Category Business, Corporate Entity Not Tax Exempt, Foreign Owned, Foreign-Owned and U.S.-Incorporated Business, Manufacturer of Goods, Not Designated a Small Business, Special Designations

Financial Breakdown

Contract Ceiling: $189,717,659

Exercised Options: $163,799,711

Current Obligation: $163,799,711

Contract Characteristics

Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED

Cost or Pricing Data: NO

Timeline

Start Date: 2021-12-15

Current End Date: 2032-09-27

Potential End Date: 2032-09-27 00:00:00

Last Modified: 2025-09-11

More Contracts from Voith Hydro Inc

View all Voith Hydro Inc federal contracts →

Other Department of Defense Contracts

View all Department of Defense contracts →

Explore Related Government Spending