Glendo Dam Modification Contract Awarded for $19.85M to Johnson-Wilson Constructors, Inc
Contract Overview
Contract Amount: $19,848,883 ($19.8M)
Contractor: Johnson-Wilson Constructors, Inc.
Awarding Agency: Department of the Interior
Start Date: 2010-09-15
End Date: 2013-12-05
Contract Duration: 1,177 days
Daily Burn Rate: $16.9K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 9
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: GLENDO DAM MODIFICATION
Place of Performance
Location: GLENDO, PLATTE County, WYOMING, 82213
State: Wyoming Government Spending
Plain-Language Summary
Department of the Interior obligated $19.8 million to JOHNSON-WILSON CONSTRUCTORS, INC. for work described as: GLENDO DAM MODIFICATION Key points: 1. Contract value of $19.85 million for dam modification. 2. Awarded to Johnson-Wilson Constructors, Inc. under full and open competition. 3. Project duration of 1177 days. 4. No small business participation noted.
Value Assessment
Rating: fair
The contract value of $19.85 million for the Glendo Dam Modification appears reasonable given the scope of heavy civil engineering construction. Benchmarking against similar dam modification projects would provide a more precise assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded through full and open competition, suggesting a competitive bidding process that should have driven price discovery. The use of a firm fixed price contract further aims to control costs.
Taxpayer Impact: The competitive nature of the award is positive for taxpayers, likely resulting in a fair market price for the dam modification services.
Public Impact
Ensures continued structural integrity and operational capacity of the Glendo Dam. Supports regional water management and infrastructure reliability. Potential for localized economic impact through construction activities.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Lack of small business participation.
- Potential for cost overruns in large-scale construction projects.
Positive Signals
- Awarded under full and open competition.
- Firm fixed price contract structure.
Sector Analysis
This contract falls within the heavy and civil engineering construction sector, specifically related to infrastructure maintenance and modification. Spending in this sector can vary significantly based on federal infrastructure needs and funding allocations.
Small Business Impact
The data indicates no small business participation in this contract. Efforts to ensure small business inclusion in future large-scale infrastructure projects could be explored.
Oversight & Accountability
The Bureau of Reclamation, under the Department of the Interior, is responsible for overseeing this project. Standard procurement and contract management oversight processes are expected to be in place.
Related Government Programs
- Other Heavy and Civil Engineering Construction
- Department of the Interior Contracting
- Bureau of Reclamation Programs
Risk Flags
- No small business participation.
- Potential for scope creep in large construction projects.
- Reliance on a single contractor for a significant infrastructure project.
Tags
other-heavy-and-civil-engineering-constr, department-of-the-interior, wy, definitive-contract, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of the Interior awarded $19.8 million to JOHNSON-WILSON CONSTRUCTORS, INC.. GLENDO DAM MODIFICATION
Who is the contractor on this award?
The obligated recipient is JOHNSON-WILSON CONSTRUCTORS, INC..
Which agency awarded this contract?
Awarding agency: Department of the Interior (Bureau of Reclamation).
What is the total obligated amount?
The obligated amount is $19.8 million.
What is the period of performance?
Start: 2010-09-15. End: 2013-12-05.
What was the specific scope of work for the Glendo Dam Modification, and how did it compare to similar projects in terms of cost-effectiveness?
The provided data does not detail the specific scope of work for the Glendo Dam Modification. A comprehensive cost-effectiveness analysis would require comparing the project's deliverables, complexity, and final cost against benchmarks from similar dam modification projects undertaken by federal or state agencies.
What were the primary risks identified during the bidding process for this contract, and how were they mitigated?
The data does not specify the risks identified during the bidding process. However, typical risks for such projects include unforeseen site conditions, material cost fluctuations, and contractor performance issues. Mitigation strategies would likely involve detailed site investigations, robust contract terms, and performance bonds.
How effectively did the full and open competition process ensure the best value for taxpayer dollars on this project?
The full and open competition process is designed to foster a competitive environment, theoretically leading to the best value. The presence of multiple bids and the final award price relative to initial estimates would indicate the effectiveness of this process in securing a fair price for the Glendo Dam Modification.
Industry Classification
NAICS: Construction › Other Heavy and Civil Engineering Construction › Other Heavy and Civil Engineering Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCT NONBUILDING FACILITIES
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: SEALED BID
Solicitation ID: R10PS60186
Offers Received: 9
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 420 WILKINSON ST, HELENA, MT, 59601
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Emerging Small Business, Small Business, Special Designations, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $19,848,883
Exercised Options: $19,848,883
Current Obligation: $19,848,883
Contract Characteristics
Multi-Year Contract: Yes
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Cost or Pricing Data: NO
Timeline
Start Date: 2010-09-15
Current End Date: 2013-12-05
Potential End Date: 2013-12-05 00:00:00
Last Modified: 2016-07-23
Other Department of the Interior Contracts
- Department of Health and Human Services, Administration of Children and Families, Office of Refugee Resettlement's Legal Services for Unaccompanied Children — $832.4M (Acacia Center for Justice)
- Military Family Life Counseling Program Igf::ot::igf — $638.8M (MHN Government Services LLC)
- Military Family Life Counseling Program — $637.0M (Magellan Healthcare Inc)
- Grants Program Solutions and Information Technology Support Services — $446.3M (Guidehouse Digital LLC)
- THE Purpose of This Requirement for Grants Program Solutions and IT Support Services IS to Provide Efficient and Effective Grant, Financial, and Contract Management Services, IT Solutions, and Support to the Grantsolutions and ITS Partners — $403.1M (Guidehouse Inc.)