DOT Awards $40.8M Design/Build Contract for Alaska Road Project to Kiewit Infrastructure West Co
Contract Overview
Contract Amount: $40,834,161 ($40.8M)
Contractor: Kiewit Infrastructure West CO.
Awarding Agency: Department of Transportation
Start Date: 2012-08-02
End Date: 2014-09-12
Contract Duration: 771 days
Daily Burn Rate: $53.0K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 1
Pricing Type: FIRM FIXED PRICE
Sector: Transportation
Official Description: IGF::CT::IGF CRITICAL FUNCTIONS AK PFH 43(10) DEWEYVILLE TRAILHEAD TO NECK LAKE ROAD (DESIGN/BUILD)
Place of Performance
Location: KLAWOCK, PRINCE OF WALES-HYDER County, ALASKA, 99925, UNITED STATES OF AMERICA
State: Alaska Government Spending
Plain-Language Summary
Department of Transportation obligated $40.8 million to KIEWIT INFRASTRUCTURE WEST CO. for work described as: IGF::CT::IGF CRITICAL FUNCTIONS AK PFH 43(10) DEWEYVILLE TRAILHEAD TO NECK LAKE ROAD (DESIGN/BUILD) Key points: 1. The contract value of $40.8M is significant for a single infrastructure project. 2. Kiewit Infrastructure West Co. is a major player in heavy civil construction, indicating strong competition. 3. The project's success hinges on timely completion and adherence to design/build specifications. 4. This falls within the Highway, Street, and Bridge Construction sector, a critical area for transportation infrastructure.
Value Assessment
Rating: good
The contract was awarded using a Firm Fixed Price (FFP) structure, which shifts risk to the contractor and provides cost certainty. Benchmarking against similar large-scale design/build highway projects is necessary for a precise value assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under full and open competition, suggesting a robust price discovery process. This method typically leads to more competitive pricing as multiple bidders vie for the contract.
Taxpayer Impact: Full and open competition generally benefits taxpayers by driving down costs through market forces.
Public Impact
Improved transportation infrastructure in Alaska, potentially boosting local commerce and accessibility. Job creation associated with the construction project. Potential for increased traffic flow and reduced travel times upon completion.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for cost overruns if unforeseen geological or environmental issues arise during design/build.
- Risk of schedule delays impacting the overall project timeline.
- Ensuring quality of construction meets federal and state standards.
Positive Signals
- Firm Fixed Price contract provides cost certainty.
- Awarded through full and open competition, suggesting competitive pricing.
- Experienced contractor selected for a complex project.
Sector Analysis
This project falls under the Highway, Street, and Bridge Construction sector. Spending in this sector is crucial for national and regional transportation networks. Benchmarks vary widely based on project scope, location, and complexity.
Small Business Impact
The data does not indicate any specific subcontracting requirements for small businesses on this contract. Further investigation would be needed to determine if small business participation was mandated or achieved.
Oversight & Accountability
The Federal Highway Administration (FHWA) is responsible for overseeing this project. Oversight would typically involve monitoring progress, ensuring compliance with contract terms, and managing any change orders.
Related Government Programs
- Highway, Street, and Bridge Construction
- Department of Transportation Contracting
- Federal Highway Administration Programs
Risk Flags
- Potential for unforeseen site conditions impacting cost and schedule.
- Complexity of a design/build contract requiring close coordination.
- Dependency on timely completion for downstream transportation benefits.
- Contractor's financial stability and past performance on similar projects.
Tags
highway-street-and-bridge-construction, department-of-transportation, ak, dca, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Transportation awarded $40.8 million to KIEWIT INFRASTRUCTURE WEST CO.. IGF::CT::IGF CRITICAL FUNCTIONS AK PFH 43(10) DEWEYVILLE TRAILHEAD TO NECK LAKE ROAD (DESIGN/BUILD)
Who is the contractor on this award?
The obligated recipient is KIEWIT INFRASTRUCTURE WEST CO..
Which agency awarded this contract?
Awarding agency: Department of Transportation (Federal Highway Administration).
What is the total obligated amount?
The obligated amount is $40.8 million.
What is the period of performance?
Start: 2012-08-02. End: 2014-09-12.
What was the total number of bids received for this contract?
The provided data indicates only one award (no: 1), but does not specify the total number of bids submitted. Full and open competition implies multiple bids were likely solicited, but the exact number is not detailed here. Understanding the bid landscape is crucial for assessing the competitiveness of the final award price.
How does the awarded amount compare to the original cost estimate for this project?
The data provides the awarded amount ($40.8M) but does not include the original cost estimate or any pre-competition estimates. Comparing the award to estimates would reveal if the project came in under, at, or over budget expectations, providing insight into the accuracy of initial planning and the effectiveness of the procurement process.
Were there any significant change orders or contract modifications during the project's lifecycle?
The provided data reflects the initial award details and does not contain information on subsequent contract modifications or change orders. Analyzing change orders is essential for understanding project evolution, potential scope creep, and any impact on the final cost and schedule beyond the initial contract terms.
Industry Classification
NAICS: Construction › Highway, Street, and Bridge Construction › Highway, Street, and Bridge Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE
Solicitation ID: DTFH70-12-R-00006
Offers Received: 1
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 2200 COLUMBIA HOUSE BLVD, VANCOUVER, WA, 98661
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Not Designated a Small Business, Special Designations, U.S.-Owned Business
Financial Breakdown
Contract Ceiling: $40,834,161
Exercised Options: $40,834,161
Current Obligation: $40,834,161
Subaward Activity
Number of Subawards: 2
Total Subaward Amount: $2,796,700
Contract Characteristics
Cost or Pricing Data: NO
Timeline
Start Date: 2012-08-02
Current End Date: 2014-09-12
Potential End Date: 2014-09-12 00:00:00
Last Modified: 2015-07-14
More Contracts from Kiewit Infrastructure West CO.
- Port of Nome Modification Phase 1A, Nome, Alaska — $399.4M (Department of Defense)
- JBE054 Runway Extension, Jber, Alaska — $377.3M (Department of Defense)
- This IS the Award for Phase IV of the Folsom JFP — $326.8M (Department of Defense)
- Yose 196416 Rehabilitate EL Portal Wastewater Treatment Facility and Administrative Camp the Work of This Contract IS for the Construction OF: Yose 196416 Rehabilitate EL Portal Wastewater Treatment Facility and Administrative Camp in Yosemite NAT — $217.7M (Department of the Interior)
- Construction of MUD Mountain DAM Fish Passage Facility in Buckley, WA — $152.7M (Department of Defense)
Other Department of Transportation Contracts
- Dafis UDO Reconstruct W/O Advance — $3.8B (Lockheed Martin Services, LLC)
- THE Purpose of This Delivery Order Award IS to ADD Funding for FTI Telecommunications Services — $1.9B (Harris Corporation)
- Provide Funding for Clin 302 for Pre-Flight and In-Flight Services. Contract Number Dtfawa-05-C-00031, Lockheed Martin. POP 01/16/08-03/31/08 — $1.9B (Leidos, Inc.)
- Center for Advanced Aviation Development (caasd) Ffrdc Mitre — $1.7B (THE Mitre Corporation)
- Dafis UDO Reconstruct W/O Advance — $1.5B (Harris Corporation)