GSA Awards $6.76M Renovation Contract for Federal Building in Springfield, IL
Contract Overview
Contract Amount: $6,756,235 ($6.8M)
Contractor: Richard Group LLC
Awarding Agency: General Services Administration
Start Date: 2022-05-13
End Date: 2026-06-20
Contract Duration: 1,499 days
Daily Burn Rate: $4.5K/day
Competition Type: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Number of Offers Received: 3
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: TASK ORDER AWARD FOR THE 3RD FLOOR USMS DETENTION AREA AND COURTS JURY ASSEMBLY ROOM RENOVATION PROJECT TAKING PLACE AT THE PAUL FINDLEY FEDERAL BUILDING & U.S. COURTHOUSE IN SPRINGFIELD, ILLINOIS
Place of Performance
Location: SPRINGFIELD, SANGAMON County, ILLINOIS, 62701
State: Illinois Government Spending
Plain-Language Summary
General Services Administration obligated $6.8 million to RICHARD GROUP LLC for work described as: TASK ORDER AWARD FOR THE 3RD FLOOR USMS DETENTION AREA AND COURTS JURY ASSEMBLY ROOM RENOVATION PROJECT TAKING PLACE AT THE PAUL FINDLEY FEDERAL BUILDING & U.S. COURTHOUSE IN SPRINGFIELD, ILLINOIS Key points: 1. The contract is for renovation of the 3rd floor detention area and jury assembly room at the Paul Findley Federal Building. 2. Awarded to RICHARD GROUP LLC, the project has a duration of 1499 days. 3. The contract type is Firm Fixed Price, indicating a set cost for the work. 4. This project falls under Commercial and Institutional Building Construction. 5. The award was made under Full and Open Competition after Exclusion of Sources.
Value Assessment
Rating: good
The contract value of $6.76 million for a multi-year renovation project appears reasonable given the scope. Benchmarking against similar federal building renovation projects of this size and complexity would provide a more definitive assessment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The procurement method was 'Full and Open Competition after Exclusion of Sources'. While this indicates competition, the exclusion of specific sources might limit the breadth of competitive offers and potentially impact price discovery.
Taxpayer Impact: Taxpayers benefit from a competitive bidding process, though the specific exclusion of sources warrants further scrutiny to ensure optimal value.
Public Impact
Enhances security and functionality of the federal courthouse. Supports judicial operations by improving jury facilities. Contributes to the modernization of federal infrastructure. Creates construction jobs in the Springfield, Illinois area.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Potential for cost overruns due to long project duration.
- Scope creep could impact final cost and timeline.
- Limited information on specific exclusion of sources.
Positive Signals
- Firm Fixed Price contract provides cost certainty.
- Renovation addresses critical functional needs.
- Competition, even with exclusions, likely drove a reasonable price.
Sector Analysis
This contract falls within the Commercial and Institutional Building Construction sector. Federal spending in this sector often involves significant infrastructure upgrades and maintenance, with costs varying widely based on project scale, location, and complexity.
Small Business Impact
The data indicates that small business participation was not a stated factor in this award (ss: false, sb: false). Further analysis would be needed to determine if subcontracting opportunities were made available to small businesses.
Oversight & Accountability
The General Services Administration (GSA), through its Public Buildings Service, is responsible for overseeing federal building projects. Oversight mechanisms should ensure adherence to schedule, budget, and quality standards throughout the renovation.
Related Government Programs
- Commercial and Institutional Building Construction
- General Services Administration Contracting
- Public Buildings Service Programs
Risk Flags
- Long project duration increases risk of cost escalation.
- Potential for scope creep impacting budget and timeline.
- Exclusion of sources may limit competitive pricing.
- Lack of explicit small business participation noted.
Tags
commercial-and-institutional-building-co, general-services-administration, il, delivery-order, 1m-plus
Frequently Asked Questions
What is this federal contract paying for?
General Services Administration awarded $6.8 million to RICHARD GROUP LLC. TASK ORDER AWARD FOR THE 3RD FLOOR USMS DETENTION AREA AND COURTS JURY ASSEMBLY ROOM RENOVATION PROJECT TAKING PLACE AT THE PAUL FINDLEY FEDERAL BUILDING & U.S. COURTHOUSE IN SPRINGFIELD, ILLINOIS
Who is the contractor on this award?
The obligated recipient is RICHARD GROUP LLC.
Which agency awarded this contract?
Awarding agency: General Services Administration (Public Buildings Service).
What is the total obligated amount?
The obligated amount is $6.8 million.
What is the period of performance?
Start: 2022-05-13. End: 2026-06-20.
What was the rationale for excluding specific sources in the 'Full and Open Competition after Exclusion of Sources' method?
The rationale for excluding specific sources typically involves technical requirements, past performance issues, or specific security clearances that only a limited number of contractors can meet. Understanding the precise reasons is crucial to assess if the exclusion was justified and did not unduly restrict competition, potentially leading to a higher price for taxpayers.
How does the $6.76 million cost benchmark against similar federal courthouse renovation projects?
Benchmarking this $6.76 million award against similar federal courthouse renovations requires detailed comparison of project scope, square footage, complexity of systems (e.g., HVAC, security), and geographic location. Without specific comparable data, it's difficult to definitively state if this price is high or low, but the long duration suggests a substantial scope of work.
What are the potential risks associated with the 1499-day project duration?
A 1499-day (approximately 4 years) duration presents risks such as material cost inflation, potential for design changes, contractor performance degradation over time, and extended disruption to building operations. Robust project management and contingency planning are essential to mitigate these risks and ensure the project stays within budget and meets its objectives.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: MAINT, REPAIR, ALTER REAL PROPERTY › MAINT, ALTER, REPAIR NONBUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Solicitation Procedures: SUBJECT TO MULTIPLE AWARD FAIR OPPORTUNITY
Solicitation ID: 47PF0022Q0029
Offers Received: 3
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 1850 JOHNS DR, GLENVIEW, IL, 60025
Business Categories: Category Business, Corporate Entity Not Tax Exempt, Limited Liability Corporation, Service Disabled Veteran Owned Business, Small Business, Special Designations, U.S.-Owned Business, Veteran Owned Business
Financial Breakdown
Contract Ceiling: $6,756,235
Exercised Options: $6,756,235
Current Obligation: $6,756,235
Contract Characteristics
Commercial Item: COMMERCIAL PRODUCTS/SERVICES PROCEDURES NOT USED
Cost or Pricing Data: NO
Parent Contract
Parent Award PIID: 47PF0018D0075
IDV Type: IDC
Timeline
Start Date: 2022-05-13
Current End Date: 2026-06-20
Potential End Date: 2026-07-20 00:00:00
Last Modified: 2026-03-31
More Contracts from Richard Group LLC
- THE Contractor Shall Provide ALL Tools, Equipment, Materials, Labor, Supervision, Personnel, and Shall DO ALL Things Necessary That Will Result in the Completion of the Ehrm Infra. UPG. Hines IL Construction Project Consistent With Specs and Drawings — $75.8M (Department of Veterans Affairs)
- Ehrm Infrastructure Upgrades - Central Western Massachusetts — $65.4M (Department of Veterans Affairs)
- Erhm Battle Creek Infrastructure Upgrades Construction — $52.9M (Department of Veterans Affairs)
- Contractor to Provide Construction Services to Complete the Ehrm Project AT the Minneapolis Vamc — $51.6M (Department of Veterans Affairs)
- Construct Surgical Intensive Care Unit (sicu) and Renovate Operating Rooms (OR) Okvamc, Oklahoma City, OK — $42.5M (Department of Veterans Affairs)
Other General Services Administration Contracts
- Software Life Cycle Development — $1.4B (Science Applications International Corporation)
- Task Order (TO) 47qfca21f0018 IS Hereby Awarded to Booz Allen Hamilton, Inc. (BAH) to Provide Enterprise Level Data to the Ousd(c), and ITS Strategic Partners (I.E., DOD Fourth Estate, DOD Departments, and IC Community) — $1.4B (Booz Allen Hamilton Inc)
- Federal Contract — $1.2B (Booz Allen Hamilton Inc)
- THE Scope of the to IS to Provide Enterprise IT Services for the Usace — $1.1B (Science Applications International Corporation)
- Task Order Award — $1.1B (Booz Allen Hamilton Inc)