DoD Awards $54.4M for DFAC Area Conversion to Brasfield & Gorrie LLC
Contract Overview
Contract Amount: $54,446,801 ($54.4M)
Contractor: Brasfield & Gorrie LLC
Awarding Agency: Department of Defense
Start Date: 2012-08-10
End Date: 2015-11-09
Contract Duration: 1,186 days
Daily Burn Rate: $45.9K/day
Competition Type: FULL AND OPEN COMPETITION
Number of Offers Received: 53
Pricing Type: FIRM FIXED PRICE
Sector: Construction
Official Description: CONSTRUCT DFAC AREA CONVERSION
Place of Performance
Location: BIRMINGHAM, JEFFERSON County, ALABAMA, 35233
State: Alabama Government Spending
Plain-Language Summary
Department of Defense obligated $54.4 million to BRASFIELD & GORRIE LLC for work described as: CONSTRUCT DFAC AREA CONVERSION Key points: 1. Significant contract value of $54.4 million awarded. 2. Full and open competition was utilized, suggesting a competitive bidding process. 3. The contract duration of 1186 days indicates a substantial project timeline. 4. The project falls under Commercial and Institutional Building Construction sector.
Value Assessment
Rating: fair
The contract value of $54.4 million for a DFAC area conversion is substantial. Without specific per-unit cost data or detailed project scope, a direct pricing comparison to similar contracts is difficult. However, the scale suggests a significant investment.
Cost Per Unit: N/A
Competition Analysis
Competition Level: full-and-open
The contract was awarded under full and open competition, which typically allows for the widest possible range of bidders and promotes competitive pricing. The use of a Delivery Order under a larger contract structure suggests a phased approach to awarding work.
Taxpayer Impact: Full and open competition generally aims to secure the best value for taxpayers by fostering a competitive environment that drives down costs.
Public Impact
Impacts military personnel by improving dining facilities. Supports the construction industry and local economy in Alabama. Represents a significant investment in military infrastructure modernization.
Waste & Efficiency Indicators
Waste Risk Score: 50 / 10
Warning Flags
- Lack of specific per-unit cost data for benchmarking.
- Contract duration is lengthy, potentially leading to cost overruns if not managed effectively.
Positive Signals
- Awarded under full and open competition.
- Firm Fixed Price contract type helps control costs.
Sector Analysis
This contract falls within the Commercial and Institutional Building Construction sector. Spending in this sector is crucial for maintaining and upgrading government facilities, including military installations. Benchmarks for similar construction projects would be needed for a precise comparison.
Small Business Impact
The data indicates that Brasfield & Gorrie LLC, a large business, was awarded this contract. There is no explicit information provided on small business participation or subcontracting goals within this specific award.
Oversight & Accountability
The award was made by the Department of the Army, a component of the Department of Defense. Oversight would typically involve contract management and performance monitoring by the contracting officer and relevant government agencies to ensure compliance and quality.
Related Government Programs
- Commercial and Institutional Building Construction
- Department of Defense Contracting
- Department of the Army Programs
Risk Flags
- Lengthy contract duration.
- Lack of detailed cost breakdown for per-unit analysis.
- No explicit mention of small business subcontracting.
- Potential for cost escalation over the project's multi-year timeline.
Tags
commercial-and-institutional-building-co, department-of-defense, al, delivery-order, 10m-plus
Frequently Asked Questions
What is this federal contract paying for?
Department of Defense awarded $54.4 million to BRASFIELD & GORRIE LLC. CONSTRUCT DFAC AREA CONVERSION
Who is the contractor on this award?
The obligated recipient is BRASFIELD & GORRIE LLC.
Which agency awarded this contract?
Awarding agency: Department of Defense (Department of the Army).
What is the total obligated amount?
The obligated amount is $54.4 million.
What is the period of performance?
Start: 2012-08-10. End: 2015-11-09.
What was the specific scope of work for the DFAC area conversion, and how does the $54.4 million cost align with industry standards for similar projects?
The specific scope of work for the DFAC area conversion is not detailed in the provided data. To assess the $54.4 million cost, a detailed breakdown of the project's requirements, such as square footage, renovation complexity, materials, and labor, would be necessary. Comparing this to industry benchmarks for similar-sized and complex facility upgrades would reveal if the cost is competitive or excessive.
Given the 1186-day duration, what are the potential risks associated with project delays and cost escalations, and what mitigation strategies were likely employed?
A long project duration like 1186 days presents risks of inflation, material price fluctuations, and unforeseen site conditions. Mitigation strategies could include robust contract clauses for managing changes, regular progress reviews, contingency planning, and strong project management by both the contractor and the government to identify and address issues proactively.
How effectively did the 'full and open competition' process ensure the best value for taxpayers on this $54.4 million contract?
Full and open competition is designed to maximize the number of potential bidders, thereby fostering a competitive environment that should lead to better pricing and value. The effectiveness in this case depends on the number and quality of bids received, the evaluation criteria used, and whether the winning bid truly represented the best combination of price and technical merit for the government's needs.
Industry Classification
NAICS: Construction › Nonresidential Building Construction › Commercial and Institutional Building Construction
Product/Service Code: CONSTRUCT OF STRUCTURES/FACILITIES › CONSTRUCTION OF BUILDINGS
Competition & Pricing
Extent Competed: FULL AND OPEN COMPETITION
Solicitation Procedures: NEGOTIATED PROPOSAL/QUOTE
Solicitation ID: W912HN09R0088
Offers Received: 53
Pricing Type: FIRM FIXED PRICE (J)
Evaluated Preference: NONE
Contractor Details
Address: 3021 7TH AVE S, BIRMINGHAM, AL, 35233
Business Categories: Category Business, Limited Liability Corporation, Not Designated a Small Business
Financial Breakdown
Contract Ceiling: $54,760,801
Exercised Options: $54,446,801
Current Obligation: $54,446,801
Contract Characteristics
Commercial Item: COMMERCIAL ITEM PROCEDURES NOT USED
Cost or Pricing Data: NO
Parent Contract
Parent Award PIID: W912HN10D0046
IDV Type: IDC
Timeline
Start Date: 2012-08-10
Current End Date: 2015-11-09
Potential End Date: 2015-11-09 00:00:00
Last Modified: 2017-08-31
More Contracts from Brasfield & Gorrie LLC
- Academic Zone Design-Build Project, Redstone Arsenal, Alabama — $519.3M (Department of Justice)
- Design and Construction of the Technology Buildings 2 & 3 With Parking Garages — $406.5M (Department of Justice)
- Package 4, Hospital Build OUT — $318.5M (Department of Veterans Affairs)
- Design Build Construction for Gateway Land Port of Entry Modernization Project, Brownsville, TX — $263.4M (General Services Administration)
- Design-Build Construction Services for a NEW U. S. Federal Building Located AT Fort Lauderdale, FL 33316- — $211.6M (General Services Administration)
Other Department of Defense Contracts
- Federal Contract — $51.3B (Humana Government Business Inc)
- Lrip LOT 12 Advance Acquisition Contract — $35.1B (Lockheed Martin Corporation)
- SSN 802 and 803 Long Lead Time Material — $34.7B (Electric Boat Corporation)
- 200204!008532!1700!AF600 !naval AIR Systems Command !N0001902C3002 !A!N! !N! !20011026!20120430!008016958!008016958!834951691!n!lockheed Martin Corporation !lockheed Blvd !fort Worth !tx!76108!27000!439!48!fort Worth !tarrant !texas !+000026000000!n!n!018981928201!ac15!rdte/Aircraft-Eng/Manuf Develop !a1a!airframes and Spares !2ama!jast/Jsf !336411!E! !3! ! ! ! ! !99990909!B! ! !A! !a!n!r!2!002!n!1a!a!n!z! ! !N!C!N! ! ! !a!a!a!a!000!a!c!n! ! ! !Y! !N00019!0001! — $34.2B (Lockheed Martin Corporation)
- KC-X Modernization Program — $32.0B (THE Boeing Company)